Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Jun 2021 Pack 1.work in progress. Pack 2.Work stopped due to death of contractor. Pack III.Work started after a long gap. Pack 4.Work to be re-tender Koothuparamba Proj AE 2
15 Jun 2021 Pack 1.Work in progress Pack 2.stopped due to death of contractor Pack 3.Work restarted after a long gap Pack 4.Re-tendered.No response Koothuparamba Proj AE 2
10 Jun 2021 Pack.1 (Clearwater tank RCC completed,Intake well steining 12 m completed, Leading channel completed, Retaining wall Completed, Clarifier floor slab completed, Filter house floor slab completed, Pack 2.(Gravity main Pipe laying work 3850 m 0ut of 4450 mt completed) Pack 3.(Work just started and only a little qty.of pipe supplied) Pack 4.(Work tendered but not success) Koothuparamba Proj AE 2
04 Feb 2021 First stage of Side wall concrete of clear water sump complted and second stage work started.Clarifier earth work and PCC completed Koothuparamba Proj AE 2
28 Jan 2021 Package I. Side wall of Clear water Sump - concrete work in progress.Clarifier PCC complted.Filter house ready for PCC. Koothuparamba Proj AE 2
18 Dec 2020 Package - I - Intake well cum pum house - steining upto 3.5 m completed, pumping main - pipe supplied, WTP - Construction of GLSR in progress, Package II -Common gravity main from WTP to Manjalampuram - Pipe supplied Koothuparamba Proj AE 2
16 Nov 2020 Work in progress Koothuparamba Proj AE 2