| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Jun 2021 | Pack 1.work in progress. Pack 2.Work stopped due to death of contractor. Pack III.Work started after a long gap. Pack 4.Work to be re-tender | Koothuparamba Proj AE 2 | |
| 15 Jun 2021 | Pack 1.Work in progress Pack 2.stopped due to death of contractor Pack 3.Work restarted after a long gap Pack 4.Re-tendered.No response | Koothuparamba Proj AE 2 | |
| 10 Jun 2021 | Pack.1 (Clearwater tank RCC completed,Intake well steining 12 m completed, Leading channel completed, Retaining wall Completed, Clarifier floor slab completed, Filter house floor slab completed, Pack 2.(Gravity main Pipe laying work 3850 m 0ut of 4450 mt completed) Pack 3.(Work just started and only a little qty.of pipe supplied) Pack 4.(Work tendered but not success) | Koothuparamba Proj AE 2 | |
| 04 Feb 2021 | First stage of Side wall concrete of clear water sump complted and second stage work started.Clarifier earth work and PCC completed | Koothuparamba Proj AE 2 | |
| 28 Jan 2021 | Package I. Side wall of Clear water Sump - concrete work in progress.Clarifier PCC complted.Filter house ready for PCC. | Koothuparamba Proj AE 2 | |
| 18 Dec 2020 | Package - I - Intake well cum pum house - steining upto 3.5 m completed, pumping main - pipe supplied, WTP - Construction of GLSR in progress, Package II -Common gravity main from WTP to Manjalampuram - Pipe supplied | Koothuparamba Proj AE 2 | |
| 16 Nov 2020 | Work in progress | Koothuparamba Proj AE 2 |