| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 01 Feb 2022 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. Retaining wall completed. Electrical room completed.Pump house completed. WTP-Clarifoculator completed.Filter completed.Wash water tank completed.Clear water tank completed . Raw water pipe line work completed . Aerator work completed.Compound wall work in progress. Pack 2.Work re started.But no progress. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in almost completed.Earth work of sump at Memala completed. PCC done.Base slab reinforcement work started. Pack 4.Estimate recalculated and submitted .Package-V-Tendered. 2 offers received. Over all progress 45%, Bill for 75% of the completed project submitted,balance bill under preparation | Koothuparamba Proj AE 2 | |
| 31 Jan 2022 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. Retaining wall completed. Electrical room completed.Pump house completed. WTP--Clarifoculator completed.Filter completed.Wash water tank completed.Clear water tank completed . Raw water pipe line work completed . Aerator work completed.Compound wall work in progress. Pack 2.Work re started.But no progress. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in almost completed.Earth work of sump at Memala completed.PCC done.Base slab reinforcement work started.Very slow progress. Pack 4.Work order issued.But agreement not executed. | Koothuparamba Proj AE 2 | |
| 25 Jan 2022 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. Retaining wall completed. Electrical room completed.Pump house completed. WTP--Clarifoculator completed.Filter completed.Wash water tank completed.Clear water tank completed . Raw water pipe line work 75% completed . Aerator work almost completed.Compound wall work in progress. Pack 2.Work re started.But no progress. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in almost completed.Earth work of sump at Memala completed.PCC done.Base slab reinforcement work started.Very slow progress. Pack 4.Work order issued.But agreement not executed. | Koothuparamba Proj AE 2 | |
| 23 Jan 2022 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room completed.Pump house completed. WTP--Clarifoculator completed.Filter completed.Wash water tank completed.Clear water tank completed . Raw water pipe line work 75% completed . Aerator work almost completed.Compound wall work in progress. Pack 2.Work re started.But no progress. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in almost completed.Earth work of sump at Memala completed.PCC done.Base slab reinforcement work started.Very slow progress. Pack 4.Work order issued.But agreement not executed. | Koothuparamba Proj AE 2 | |
| 19 Jan 2022 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room completed.Pump house completed. WTP--Clarifoculator completed.Filter house near in completion.Wash water tank completed.Clear water tank finishing work completed . Raw water pipe line work ,75% completed.Stopped due to a road issue . Aerator work almost completed.Compound wall work in progress. Pack 2.Work re started.But no progress. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in almost completed.Earth work of sump at Memala completed.PCC done .Very slow progress. Pack 4.Work order issued.Agreement not executed. | Koothuparamba Proj AE 2 | |
| 12 Jan 2022 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room completed.Pump house completed. WTP--Clarifoculator near in completion ,finishing work in progress.Filter house finishing work in progress.Wash water tank concrete completed.Clear water tank finishing work completed . Raw water pipe line work ,75% completed.Stopped due to a road issue st. Aerator work in progress.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in progress.Earth work of sump at Memala Started.Ground levelled.Excavation for foundation started.Very slow progress. Pack 4.Work order issued.Agreement not executed. | Koothuparamba Proj AE 2 | |
| 09 Jan 2022 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room completed.Pump house completed. WTP--Clarifoculator near in completion ,finishing work in progress.Filter house finishing work in progress.Wash water tank concrete completed.Clear water tank finishing work completed . Raw water pipe line work started. Aerator work in progress.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in progress.Earth work of sump at Memala Started.Ground levelled.Excavation for foundation started.Very slow progress. Pack 4.Work order issued.Agreement not executed. | Koothuparamba Proj AE 2 | |
| 05 Jan 2022 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room completed.Pump house completed. WTP--Clarifoculator near in completion ,finishing work in progress.Filter house finishing work in progress.Wash water tank concrete completed.Clear water tank finishing work completed . Raw water pipe line work started. Aerator work in progress.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in progress.Earth work of sump at Memala Started.Ground levelled.Excavation for foundation started.Very slow progress. Pack 4.Work order issued.Agreement not executed. | Koothuparamba Proj AE 2 | |
| 03 Jan 2022 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room completed.Pump house completed. WTP--Clarifoculator near in completion ,finishing work in progress.Filter house finishing work in progress.Wash water tank concrete completed.Clear water tank finishing work completed . Raw water pipe line work started. Aerator work in progress.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in progress.Earth work of sump at Memala Started.Ground levelled.Very slow progress. Pack 4.Work order issued.Agreement not executed. | Koothuparamba Proj AE 2 | |
| 31 Dec 2021 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room completed.Pump house completed. WTP--Clarifoculator near in completion ,finishing work in progress.Filter house finishing work in progress.Wash water tank concrete completed.Clear water tank finishing work completed . Raw water pipe line work started. Aerator work in progress.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in progress.Earth work of sump at Memala Started..Very slow progress. Pack 4.Work order issued.Agreement not executed. | Koothuparamba Proj AE 2 |