| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 04 Jul 2025 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – Commisioned and Completed 4 (part -I) - Commisioned and Completed Package 4 (part II)-Commisioned and Completed , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) -Commisioned and Completed | Koothuparamba Proj AE 2 | |
| 27 Feb 2025 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – Commisioned and Completed 4 (part -I) - Commisioned and Completed Package 4 (part II)-Commisioned and Completed , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) -Commisioned and Completed | Koothuparamba Proj AE 2 | |
| 22 Feb 2025 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – Commisioned and Completed 4 (part -I) - Commisioned and Completed Package 4 (part II)-Commisioned and Completed , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) -Commisioned and Completed | Koothuparamba Proj AE 2 | |
| 11 Feb 2025 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – Charging and commisioning ongoing 4 (part -I) - Charging and commisioning ongoing Package 4 (part II)-Charging and commisioning ongoing , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) -Charging and commisioning ongoing | Koothuparamba Proj AE 2 | |
| 06 Feb 2025 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – Charging and commisioning ongoing 4 (part -I) - Charging and commisioning ongoing Package 4 (part II)-Charging and commisioning ongoing , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) -Charging and commisioning ongoing | Koothuparamba Proj AE 2 | |
| 05 Feb 2025 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – Charging and commisioning ongoing 4 (part -I) - Charging and commisioning ongoing Package 4 (part II)-Charging and commisioning ongoing , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) -Charging and commisioning ongoing | Koothuparamba Proj AE 2 | |
| 01 Feb 2025 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – Charging and commisioning ongoing 4 (part -I) - Charging and commisioning ongoing Package 4 (part II)-Charging and commisioning ongoing , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) -Charging and commisioning ongoing | Koothuparamba Proj AE 2 | |
| 24 Jan 2025 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – Charging and commisioning ongoing 4 (part -I) - Charging and commisioning ongoing Package 4 (part II)-Charging and commisioning ongoing , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) -Charging and commisioning ongoing | Koothuparamba Proj AE 2 | |
| 20 Jan 2025 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – Charging and commisioning ongoing 4 (part -I) - Charging and commisioning ongoing Package 4 (part II)-Charging and commisioning ongoing , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) -Charging and commisioning ongoing | Koothuparamba Proj AE 2 | |
| 16 Jan 2025 | Package 1- Commisioned at 20/5/2024. Package 2- Commisioned on 24/5/2024 .package 3 – Charging and commisioning ongoing 4 (part -I) - Charging and commisioning ongoing Package 4 (part II)-Charging and commisioning ongoing , Package 5 -Commissioned on 23/5/2024, Package 5 (part II) -Charging and commisioning ongoing | Koothuparamba Proj AE 2 |