| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 27 Dec 2021 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room completed.Pump house completed. WTP--Clarifoculator near in completion ,finishing work in progress.Filter house finishing work in progress.Wash water tank floor slab and side wall concreted.Clear water tank finishing work completed . Raw water pipe line work started Aerator work in progress.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in progress.Earth work of sump at Memala Started..Very low progress. Pack 4.Work order issued.Agreement not executed. | Koothuparamba Proj AE 2 | |
| 23 Dec 2021 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room completed.Pump house completed. WTP--Clarifoculator near in completion ,finishing work in progress.Filter house finishing work in progress.Wash water tank floor slab and side wall concreted.Clear water tank finishing work completed . Raw water pipe line work started Aerator work in progress.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work in progress.Earth work of sump at Memala Started..Very low progress. Pack 4.Work order issued.Agreement not executed. | Koothuparamba Proj AE 2 | |
| 19 Dec 2021 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room completed.Pump house painting work in progress. WTP--Clarifoculator near in completion ,finishing work in progress.Filter house finishing work in progress.Wash water tank floor slab concreted.Clear water tank finishing work completed . Raw water pipe line work started Aerator work in progress.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work started.Very low progress.Reccomended toEE for termination. Pack 4.Work order issued.Agreement not executed. | Koothuparamba Proj AE 2 | |
| 16 Dec 2021 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room completed.Pump house painting work in progress. WTP--Clarifoculator near in completion ,finishing work in progress.Filter house finishing work in progress.Wash water tank floor slab concreted.Clear water tank finishing work completed . Raw water pipe line work started Aerator work in progress.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work started.Very low progress.Reccomended toEE for termination. Pack 4.Work order issued.Agreement not executed. | Koothuparamba Proj AE 2 | |
| 13 Dec 2021 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room completed.Pump house painting work in progress. WTP--Clarifoculator near in completion ,finishing work in progress.Filter house finishing work in progress.Wash water tank floor slab concreted.Clear water tank finishing work completed . Raw water pipe line work started Aerator work in progress.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work started.Very low progress.Reccomended toEE for termination. Pack 4.Work order issued | Koothuparamba Proj AE 2 | |
| 10 Dec 2021 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room completed.Pump house painting work in progress. WTP--Clarifoculator near in completion ,finishing work in progress.Filter house finishing work in progress.Wash water tank floor slab concreted.Clear water tank finishing work completed . Raw water pipe line work started Aerator work in progress.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work started.Very low progress.Reccomended toEE for termination. Pack 4.Work order issued | Koothuparamba Proj AE 2 | |
| 06 Dec 2021 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room ,Plastering completed.Pump house finishing work in progress. WTP--Clarifoculator RCC completed ,finishing work in progress.Filter house RCC completed.Wash water tank floor slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started Aerator work started.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work started.Very low progress.Reccomended toEE for termination. Pack 4.Work order issued | Koothuparamba Proj AE 2 | |
| 02 Dec 2021 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room ,Plastering completed.Pump house finishing work in progress. WTP--Clarifoculator RCC completed ,finishing work in progress.Filter house RCC completed.Wash water tank floor slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started Aerator work started.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work started.Very low progress.Reccomended toEE for termination. Pack 4.Work order issued | Koothuparamba Proj AE 2 | |
| 28 Nov 2021 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room ,Plastering completed.Pump house finishing work in progress. WTP--Clarifoculator RCC completed ,finishing work in progress.Filter house RCC completed.Wash water tank floor slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started Aerator work started.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work started. Pack 4.Tender submitted to CE for sanction | Koothuparamba Proj AE 2 | |
| 25 Nov 2021 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room ,Plastering completed.Pump house finishing work in progress. WTP--Clarifoculator RCC completed ,finishing work in progress.Filter house RCC completed.Wash water tank floor slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started Aerator work started.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work started. Pack 4.Tender submitted to CE for sanction | Koothuparamba Proj AE 2 |