Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Sep 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started. Retaining wall completed. Electrical room roof slab concreted. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Clear water tank RCC completed.Finishing work started. Plinth beams completed . Raw water pipe line not started Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam started. Pack 4.Tender under scrutiny Koothuparamba Proj AE 2
06 Sep 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started. Retaining wall completed. Electrical room roof slab concreted. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Clear water tank RCC completed.Finishing work started. Plinth beams completed . Raw water pipe line not started Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam started. Pack 4.Tender under scrutiny Koothuparamba Proj AE 2
03 Sep 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started. Retaining wall completed. Electrical room roof slab concreted. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Clear water tank RCC completed.Finishing work started. Plinth beams completed . Raw water pipe line not started Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam started. Pack 4.Tender under scrutiny Koothuparamba Proj AE 2
31 Aug 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started. Retaining wall completed. Electrical room roof slab ready for concrete. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Clear water tank RCC completed.Finishing work started. Plinth beams completed . Raw water pipe line not started Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam started. Pack 4.Tender under scrutiny Koothuparamba Proj AE 2
27 Aug 2021 Pack.1.Work in progress Pack 2.Work not re started Pack 3.Work in progress Pack 4.Tender under scrutiny Koothuparamba Proj AE 2
25 Aug 2021 Pack 1.Work in progress Pack 2.Work not re started Pack 3.Slow progress Pack 4.Tender under scrutiny Koothuparamba Proj AE 2
23 Aug 2021 Pack 1.Intake well cover slab completed.Approach bridge completed.Retaining wall completed.Electrical room floor slab completed and super structutre work in progress. WTP-clarifier side wall almost completed.Filter house side wall completed.CW tank completed.Plinth beams are completed and super structure work in progress. Pack II.Work not re started Pack III.Sump work at Kambipalam only in progress.No further progress in pipe supply. Pack IV.Tender under scrutiny Koothuparamba Proj AE 2
16 Aug 2021 Pack 1.Work in progress.Intake well cover slab completed.Approach bridge completed.Retaining wall completed.WTP work in progress. PACK 2.Work not re started Pack 3.Sump at Kambipalam cover slab concreted. Pack 4.Tender under scrutiny Koothuparamba Proj AE 2
13 Aug 2021 Pack 1. Intake well cover slab completed.Approach Bridge to well completed.Electrical room floor slab completed,then wall work in progress.Retaining wall completed.Leading channel completed. Raw water pumping main not started WTP-CW sump RCC completed.Filter house side wall near in completion.Clarifier side wall concreted.All other components are in progress Pack II .work not re started. Pack III.Sump at Kambipalam concrete completed. Pack IV.Bid opened.Bid under scrutiny. Koothuparamba Proj AE 2
09 Aug 2021 Pack 1.Well steining completed.Floor slab ready for concrete.Retaining wall completed. Electrical room floor slab completed.Approach bridge work in progress.Ready for concrete. Leading channel completed WTP-CW tank concrete completed.Clarifier side wall concrete completed.Filter house side wall almost completed. Plinth beams completed.all oter components are in progress. Raw water pumping main -Pipe laying not started Pack II.Work 73% completed.Stopped due to the death of contractor.Liability uptodate is reported.Work to be re arranged .Waiting for further orders. Pack III.slow progress.Sump side wall completed.Pipe supplied only a little Quantity. Pack IV.retendered and bid opened.Single tender.Bid under scruitiny Koothuparamba Proj AE 2