Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Oct 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house , RCC completed. Plastering in progress.Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed,.Roof slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall work started. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction Koothuparamba Proj AE 2
29 Oct 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house , RCC completed. Plastering in progress.Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed,.Roof slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall work started. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction Koothuparamba Proj AE 2
27 Oct 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started.Corbel work in RCC completed. Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed,.Roof slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall work started. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sancti Koothuparamba Proj AE 2
25 Oct 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started.Corbel work in RCC completed. Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed,.Roof slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall work started. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction. Koothuparamba Proj AE 2
21 Oct 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started.Corbel work in RCC completed. Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed,.Roof slab concreted.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall work started. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction. Koothuparamba Proj AE 2
19 Oct 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started.Corbel work in RCC completed. Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed,.Roof slab concreted.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall work started. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction. Koothuparamba Proj AE 2
16 Oct 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started.Corbel work in RCC completed. Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed,.Roof slab concreted.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall boundary marked. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction. Koothuparamba Proj AE 2
13 Oct 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started.Corbel work in RCC completed. Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed,roof slab ready for concreting.Roof slab shutteing started.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall boundary marked. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction. Koothuparamba Proj AE 2
11 Oct 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started.Corbel work in RCC completed. Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Roof slab shutteing started.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall boundary marked. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction. Koothuparamba Proj AE 2
09 Oct 2021 Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started.Corbel work in RCC completed. Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Roof slab shutteing started.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall boundary marked. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction. Koothuparamba Proj AE 2