| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 06 Oct 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started.Corbel work in progress. Retaining wall completed. Electrical room roof slab concreted and wall completed. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Roof slab shutteing started.Clear water tank RCC completed.Finishing work completed . Raw water pipe line not started .Aerator work started. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction. | Koothuparamba Proj AE 2 | |
| 04 Oct 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started.Corbel work in progress. Retaining wall completed. Electrical room roof slab concreted and wall completed. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Roof slab shutteing started.Clear water tank RCC completed.Finishing work completed . Raw water pipe line not started .Aerator work started. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction. | Koothuparamba Proj AE 2 | |
| 30 Sep 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started. Retaining wall completed. Electrical room roof slab concreted and wall completed. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Clear water tank RCC completed.Finishing work started . Raw water pipe line not started .Aerator work started.Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam started,and Roof slab concreted. Pack 4.Tender submitted to CE for sanction. | Koothuparamba Proj AE 2 | |
| 28 Sep 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started. Retaining wall completed. Electrical room roof slab concreted and wall completed. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Clear water tank RCC completed.Finishing work started . Raw water pipe line not started .Aerator work started.Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam started,and Roof slab concreted. Pack 4.Tender under scrutiny | Koothuparamba Proj AE 2 | |
| 25 Sep 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started. Retaining wall completed. Electrical room roof slab concreted and wall completed. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Clear water tank RCC completed.Finishing work started . Raw water pipe line not started .Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam started,and Roof slab concreted. Pack 4.Tender under scrutiny | Koothuparamba Proj AE 2 | |
| 22 Sep 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started. Retaining wall completed. Electrical room roof slab concreted and wall completed. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Clear water tank RCC completed.Finishing work started . Raw water pipe line not started .Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam started,and Roof slab concreted. Pack 4.Tender under scrutiny | Koothuparamba Proj AE 2 | |
| 20 Sep 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started. Retaining wall completed. Electrical room roof slab concreted and wall completed. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Clear water tank RCC completed.Finishing work started . Raw water pipe line not started .Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam started,and Roof slab concreted. Pack 4.Tender under scrutiny | Koothuparamba Proj AE 2 | |
| 17 Sep 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started. Retaining wall completed. Electrical room roof slab concreted and wall completed. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Clear water tank RCC completed.Finishing work started. Plinth beams completed . Raw water pipe line not started Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam started.Roof slab concreted. Pack 4.Tender under scrutiny | Koothuparamba Proj AE 2 | |
| 15 Sep 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started. Retaining wall completed. Electrical room roof slab concreted. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Clear water tank RCC completed.Finishing work started. Plinth beams completed . Raw water pipe line not started Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam started. Pack 4.Tender under scrutiny | Koothuparamba Proj AE 2 | |
| 12 Sep 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house work started. Retaining wall completed. Electrical room roof slab concreted. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed.Clear water tank RCC completed.Finishing work started. Plinth beams completed . Raw water pipe line not started Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam started. Pack 4.Tender under scrutiny | Koothuparamba Proj AE 2 |