| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Jul 2021 | Pack 1.work in progress pack 2.Work not -re started Pack.3.Work in progress Pack.4.Re-tendered. | Koothuparamba Proj AE 2 | |
| 02 Jul 2021 | Pack.1-work in progress Pack.2.Work not re-started Pack.3.Sump work in Progress Pack.4.Re-tendered.But no response | Koothuparamba Proj AE 2 | |
| 01 Jul 2021 | Pack 1.Work in progress.WTP -work in progress Pack.2.Work not restarted Pack 3.Work in progress Pack.4.Re-tendered.Nobody submitted bid. | Koothuparamba Proj AE 2 | |
| 30 Jun 2021 | Pack.1.WTP -work in progress.Intake well-Work in progress.Pumpin main-Laying not started. Pack.2.Work not re-started. Pack.3.Sump work in Progress.Pipe line-No progress Pack.4.Re-tendered. | Koothuparamba Proj AE 2 | |
| 30 Jun 2021 | Pack.1.WTP -work in progress.Well -Work in progress.Pumping main -laying not started. | Koothuparamba Proj AE 2 | |
| 30 Jun 2021 | Well work in progress.WTP also in progress.Pumping main work not started. | Koothuparamba Proj AE 2 | |
| 29 Jun 2021 | Pack 1.Last stage of well steining ready for concrete.Retaining wall completed.Electrical room columns completed.colunmns of walkway and lansing slab in well ready for concreting .WTP work in progress. Pack 2.Work to be re-started. Pack.3.Floor slab of sump at Kambipalam completed.Reinforcement work started for side wall. Pack.4.re-tendered | Koothuparamba Proj AE 2 | |
| 28 Jun 2021 | Pack 1.Last stage of steining ready for concrete. Pack 2.Work not Re-Started. Pack 3.Floor slab of Sump at kambipalam is ready for concreting. Pack 4.re-tendered. | Koothuparamba Proj AE 2 | |
| 24 Jun 2021 | 1.Pack 1.Work in progress.Well steining last stage of steining Ready for concrete.Retaining wall completed.WTP work in progress. 2.Pack 2.work stopped due to death of contractor.Contacted to the Power of attorney holder ,asked him to contact office 3.Pack 3.PCC of Sump at Kambipalam completed. Pack.4.Re-tendered by fixing due date as 30 /06/2021 | Koothuparamba Proj AE 2 | |
| 22 Jun 2021 | Pack 1.Work in progress Pack.2.work stopped due to death of contractor Pack 3.Earth work of sump at kambipalam completed.Ready for PCC | Koothuparamba Proj AE 2 |