| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 22 Nov 2021 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room ,Plastering completed.Pump house finishing work in progress. WTP--Clarifoculator RCC completed ,finishing work in progress.Filter house RCC completed.Wash water tank floor slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started Aerator work started.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work started. Pack 4.Tender submitted to CE for sanction | Koothuparamba Proj AE 2 | |
| 19 Nov 2021 | Pack 1.intake Well and Approach bridge completed.Leading channel completed. .Retaining wall completed. Electrical room ,Plastering completed.Pump house finishing work in progress. WTP--Clarifoculator RCC completed ,finishing work in progress.Filter house RCC completed.Wash water tank floor slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started Aerator work started.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work started. Pack 4.Tender submitted to CE for sanction | Koothuparamba Proj AE 2 | |
| 17 Nov 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house , RCC completed. Plastering in progress.Retaining wall completed. Electrical room ,Plastering completed.Pump house finishing work in progress. WTP--Clarifoculator RCC completed ,finishing work in progress.Filter house RCC completed.Wash water tank floor slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started Aerator work started.Compound wall work in progress. Pack 2.Work re started. Pack 3.Pump house work of sump at Kambipalam structure completed.Finishing work started. Pack 4.Tender submitted to CE for sanction | Koothuparamba Proj AE 2 | |
| 15 Nov 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house , RCC completed. Plastering in progress.Retaining wall completed. Electrical room ,Plastering completed.Pump house finishing work in progress. WTP--Clarifoculator RCC completed ,finishing work in progress.Filter house RCC completed.Wash water tank floor slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started Aerator work started.Compound wall work in progress. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction | Koothuparamba Proj AE 2 | |
| 13 Nov 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house , RCC completed. Plastering in progress.Retaining wall completed. Electrical room ,Plastering completed.Pump house finishing work in progress. WTP--Clarifoculator RCC completed ,finishing work in progress.Filter house RCC completed.Wash water tank floor slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started Aerator work started.Compound wall work in progress. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction | Koothuparamba Proj AE 2 | |
| 11 Nov 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house , RCC completed. Plastering in progress.Retaining wall completed. Electrical room ,Plastering completed.Pump house finishing work in progress. WTP--Clarifoculator RCC completed ,finishing work in progress.Filter house RCC completed.Wash water tank floor slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started Aerator work started.Compound wall work in progress. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction | Koothuparamba Proj AE 2 | |
| 09 Nov 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house , RCC completed. Plastering in progress.Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed,.Roof slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall work in progress. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction | Koothuparamba Proj AE 2 | |
| 07 Nov 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house , RCC completed. Plastering in progress.Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed,.Roof slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall work in progress. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction | Koothuparamba Proj AE 2 | |
| 04 Nov 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house , RCC completed. Plastering in progress.Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed,.Roof slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall work started. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction | Koothuparamba Proj AE 2 | |
| 02 Nov 2021 | Pack 1.Well cover sab and Approach bridge completed.Leading channel completed.Pump house , RCC completed. Plastering in progress.Retaining wall completed. Electrical room roof slab concreted and wall completed.Plastering in progress. WTP--Clarifoculator RCC completed up to launder.Filter house side wall RCC completed,.Roof slab concreted.Finishing works in progress.Clear water tank finishing work completed . Raw water pipe line not started .Aerator work started.Compound wall work started. Pack 2.Work not re started. Pack 3.Pump house work of sump at Kambipalam structure completed. Pack 4.Tender submitted to CE for sanction | Koothuparamba Proj AE 2 |