Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
08 Aug 2021 Pack 1.Work in progress Pack 2.work to be re started Pack 3.Work in progress Pack 4.Re-tendered.Bid under scrutiny Koothuparamba Proj AE 2
05 Aug 2021 Pack 2.Work not re started Pack 3.Work in progress.Side wall of sump at kambipalam RCC completed.Other components- no progress Pack 4.Retendered.Price Bid opened.single tender.Under scruitiny Koothuparamba Proj AE 2
05 Aug 2021 Pack 1.WTP.Clarifier side wall completed.floculator wall in progress Filter house side wall concrete near in completion All plinth beams completed. Well.Steining completed.Retaining wall completed.Electrical room floor slab completed.columns in progress Bridge to well in progress. Raw water pumping main not started Koothuparamba Proj AE 2
03 Aug 2021 pack 2.Work not re started Pack 3.work in progress Pack 4.Work retendered.One bidder quoted Koothuparamba Proj AE 2
03 Aug 2021 Well work in progress.steining completed. WTP work also in progress.Clarifier side wall fist and second stage completed.all other componenets are in progress. Raw water pumping main not started Koothuparamba Proj AE 2
01 Aug 2021 Pack 1.Work in progress pack 2.work not restarted Pack 3.work in progress Pack 4.work re tendered Koothuparamba Proj AE 2
30 Jul 2021 pack 1.Work in progress.Clarifier 2nd lift ready for concrete.Well reached up to floor slab level Pack 2.work not re started pack 3.Sump work at kambipalam only in progress pack 4.Work re tendered Koothuparamba Proj AE 2
28 Jul 2021 Pack 1.Work in progress Pack 2.Work not re started Pack 3.Work in progress Pack4.Work re tendered Koothuparamba Proj AE 2
26 Jul 2021 Pack 1.work in progress.well and WTP are in progress Pack 2.Not re started Pack 3.Work of sump is in progress.other componenets are not started Pack 4.Work re tendered Koothuparamba Proj AE 2
25 Jul 2021 Pack 1.Work in progress Pack 2.Work not re started Pack 3.Work in progress Pack 4.Work re tenderd Koothuparamba Proj AE 2