| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 23 Jul 2021 | Pack 1.Work in progress Pack 2.Work not re started pack 3.Work in progress Pack 4.Work re tendered | Koothuparamba Proj AE 2 | |
| 21 Jul 2021 | Pack 1.work in progress Pack 2.work not re started Pack 3.work in progress Pack.4.Work re tendered | Koothuparamba Proj AE 2 | |
| 19 Jul 2021 | Pack 1. Work in progress.Well work 80% completed.WTP 40% completed.Raw water pumping main l-laying not started.Retaining wall completed. Pack 2.Not re started Pack 3.work in progress.Sump at kambipalam 10% completed.Pipe supply-no progress. Pack.4.Re-tendered.Due date extended to 30-07-21 | Koothuparamba Proj AE 2 | |
| 15 Jul 2021 | Pack 1.Work in progress. Pack 2.Work stopped due to death of contractor. Pack 3.Work in progress Pack 4.Re-tendered | Koothuparamba Proj AE 2 | |
| 13 Jul 2021 | Pack 1.work in progress. Pack 2.work not re started Pack 3.Work in progress Pack 4.Work re-tendered | Koothuparamba Proj AE 2 | |
| 12 Jul 2021 | Pack 1.work in progress Pack 2.Work not re started Pack 3.Work in progress Pack 4.Work re tendered | Koothuparamba Proj AE 2 | |
| 10 Jul 2021 | Pack 1.work in progress Pack 2.Work not re started Pack 3.Work in ptrogress Pack 4.Work re tendered | Koothuparamba Proj AE 2 | |
| 08 Jul 2021 | Pack 1.work in progress Pack 2.work not re started Pack 3.Work in progress Pack 4.work re tendered | Koothuparamba Proj AE 2 | |
| 06 Jul 2021 | Pack.1.Work in progress Pack.2.Work not started Pack.3.Work in progress Pack.4.Re-tendered | Koothuparamba Proj AE 2 | |
| 05 Jul 2021 | Pack.1.Electrical room floor slab ready for concrete.well steining final stage ready for concrete. Pack.2.Work not re-started Pack.3.Sump work at kambipalam in progress Pack.4.Work re-tendered | Koothuparamba Proj AE 2 |