14 Nov 2022 Supply of PVC pipe completed. Pcc work for pump house at valiyavelicham completed and laterite work stated. For OHSR earth work excavation completed and pcc work for column footing arranged on 15.11.2022 Koothuparamba Proj AE 2
10 Nov 2022 Pvc pipe supplied and reinforcement work of OHSR started Koothuparamba Proj AE 2
04 Nov 2022 pcc completed for pumphouse at valiyavelicham and pipe supplying started Koothuparamba Proj AE 2
02 Nov 2022 Earth work excavation started for OHSR and pump house at valiya velicham Koothuparamba Proj AE 2
27 Oct 2022 Earth work excavation started for OHSR Koothuparamba Proj AE 2
21 Oct 2022 Work order issued and agreement executed, Order placed for pipes Koothuparamba Proj AE 2
17 Oct 2022 Work order issued and agreement executed, Ordered for pipes Koothuparamba Proj AE 2
12 Oct 2022 Work order issued and agreement executed Koothuparamba Proj AE 2