JJM-Kannur District- WSS to Cheruvanchery village in Pattiam panchayath- Phase I- Construction of service reservoirs and laying distribution network and providing FHTCs.

Project JJM-Kannur District- WSS to Cheruvanchery village in Pattiam panchayath- Phase I- Construction of service reservoirs and laying distribution network and providing FHTCs.
Project Code KNRJJM092012330
Type Main project
Funding Agency JJM
Category JJM
Type of scheme Water Supply
Scheme 4215-01-102-92-02
Description Laying Distribution line and providing 3728 FHTC .total distribution line proposed in this project is 53235 m for main line and 19500 m for laying rider line and parellel line for avoiding road crossing.
Status On-going
District Kannur
Executing Office Kannur Project Dn
AS Amount (Rs) 254000000
AS Number G.O.(Rt)No.489/2021/WRD
TS Amount (Rs) 248000000
TS Number 10295/20212-2023
Total Bill Submitted (Rs) 136494241
Total Bill Paid (Rs) 100888959
Population Benefitted 30502
Capacity in MLD 15.00
Actual Project Completion Date 24 May 2023
Coverage Cheruvanchery village in Pattiam panchayath
Implementation Schedule Download
Work Plan Download

Packages

No. Project Name Location View
1 JJM-Kannur District- WSS to Cheruvanchery village in Pattiam panchayath- Phase I- Construction of service reservoirs and laying distribution network and providing FHTCs. Koothuparamba Project Sn No2

Overall Project Status

Status Date Overall Project Status Project Officer Contact
22 Jun 2024 77500 m pipe laid , Balance work in Mooriyad cheruvanchery road (2km) is being stopped due to monsoon ban Koothuparamba Proj AE 2
19 Jun 2024 77500 m pipe laid , Balance work progressing in Mooriyad cheruvanchery road (2km) Koothuparamba Proj AE 2
13 Jun 2024 77000 m pipe laid , Balance work progressing in Mooriyad cheruvanchery road (2km) Koothuparamba Proj AE 2
07 Jun 2024 77000 m pipe laid , Balance work progressing in Mooriyad cheruvanchery road (2km) Koothuparamba Proj AE 2
03 Jun 2024 77000 m pipe laid , Balance work progressing in Mooriyad cheruvanchery road (2km) Koothuparamba Proj AE 2

No project review have been added to this project

Duration & Sanction dates

Date of start of Project 19/09/2022
Scheduled date of Completion of the Project 24 May 2023
Expected date of Completion 30/06/2024

Processing Dates

AS Date 18 Sep 2021
TS Date 15 Jul 2022