JJM-Kannur District- WSS to Cheruvanchery village in Pattiam panchayath- Phase I- Construction of service reservoirs and laying distribution network and providing FHTCs.
Project |
JJM-Kannur District- WSS to Cheruvanchery village in Pattiam panchayath- Phase I- Construction of service reservoirs and laying distribution network and providing FHTCs. |
Project Code |
KNRJJM092012330 |
Type |
Main project |
Funding Agency |
JJM |
Category |
JJM |
Type of scheme |
Water Supply |
Scheme |
4215-01-102-92-02 |
Description |
Laying Distribution line and providing 3728 FHTC .total distribution line proposed in this project is 53235 m for main line and 19500 m for laying rider line and parellel line for avoiding road crossing. |
Status |
On-going |
District |
Kannur |
Executing Office |
Kannur Project Dn |
AS Amount (Rs) |
254000000
|
AS Number |
G.O.(Rt)No.489/2021/WRD |
TS Amount (Rs) |
248000000 |
TS Number |
10295/20212-2023 |
Total Bill Submitted (Rs) |
136494241 |
Total Bill Paid (Rs) |
100888959 |
Population Benefitted |
30502 |
Capacity in MLD |
15.00 |
Actual Project Completion Date |
24 May 2023 |
Coverage |
Cheruvanchery village in Pattiam panchayath |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
JJM-Kannur District- WSS to Cheruvanchery village in Pattiam panchayath- Phase I- Construction of service reservoirs and laying distribution network and providing FHTCs. |
Koothuparamba Project Sn No2 |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
22 Jun 2024 |
77500 m pipe laid , Balance work in Mooriyad cheruvanchery road (2km) is being stopped due to monsoon ban |
Koothuparamba Proj AE 2 |
|
19 Jun 2024 |
77500 m pipe laid , Balance work progressing in Mooriyad cheruvanchery road (2km) |
Koothuparamba Proj AE 2 |
|
13 Jun 2024 |
77000 m pipe laid , Balance work progressing in Mooriyad cheruvanchery road (2km) |
Koothuparamba Proj AE 2 |
|
07 Jun 2024 |
77000 m pipe laid , Balance work progressing in Mooriyad cheruvanchery road (2km) |
Koothuparamba Proj AE 2 |
|
03 Jun 2024 |
77000 m pipe laid , Balance work progressing in Mooriyad cheruvanchery road (2km) |
Koothuparamba Proj AE 2 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
19/09/2022 |
Scheduled date of Completion of the Project |
24 May 2023 |
Expected date of Completion |
30/06/2024 |
Processing Dates
AS Date |
18 Sep 2021 |
TS Date |
15 Jul 2022 |