Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Feb 2024 | 2200 HTC , 76745m | Koothuparamba Proj AE 2 | |
14 Feb 2024 | 2220 HTC , 76800 m pipe laid | Koothuparamba Proj AE 2 | |
09 Feb 2024 | 2200 HTC , 76742 m pipe laid. | Koothuparamba Proj AE 2 | |
05 Feb 2024 | 2200 HTC , 64650m pipe laid. | Koothuparamba Proj AE 2 | |
27 Jan 2024 | 2185 HTC , 64500m pipe laid. | Koothuparamba Proj AE 2 | |
24 Jan 2024 | 2185 HTC , 58500m pipe laid. OHSR Plastering work completed. Compound wall work at OHSR completed | Koothuparamba Proj AE 2 | |
23 Jan 2024 | 2185 HTC , 44500m pipe laid. OHSR Plastering work completed. Compound wall work at OHSR completed | Koothuparamba Proj AE 2 | |
15 Jan 2024 | 2185 HTC , 44500m pipe laid. OHSR Plastering work completed. Compound wall work started | Koothuparamba Proj AE 2 | |
09 Jan 2024 | 2165 HTC , 44000m pipe laid | Koothuparamba Proj AE 2 | |
01 Jan 2024 | 2154 HTC , 42500m pipe laid andGL tank at Arakkal colony coverslab concrete completed | Koothuparamba Proj AE 2 |