Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
04 Feb 2023 | OHSR First floor column work on progress and 15600m pipe laid | Koothuparamba Proj AE 2 | |
01 Feb 2023 | OHSR First floor column work on progress and 15300m pipe laid | Koothuparamba Proj AE 2 | |
28 Jan 2023 | OHSR First floor column work on progress and 15000m pipe laid | Koothuparamba Proj AE 2 | |
25 Jan 2023 | Ground floor slab OHSR concrete completed and 15000m pipe laid | Koothuparamba Proj AE 2 | |
20 Jan 2023 | Reinforcement work for ground floor slab OHSR started and 14500m pipe laid | Koothuparamba Proj AE 2 | |
18 Jan 2023 | Form work for ground floor slab OHSR completed and 14000m pipe laid | Koothuparamba Proj AE 2 | |
16 Jan 2023 | Form work for ground floor slab OHSR started | Koothuparamba Proj AE 2 | |
13 Jan 2023 | 13000m pipe laid | Koothuparamba Proj AE 2 | |
06 Jan 2023 | Columns concreting upto 3metre above plinth level for OHSR completed and 12600m pipe laid | Koothuparamba Proj AE 2 | |
04 Jan 2023 | Columns concreting upto 2metre above plinth level for OHSR completed and 12000m pipe laid | Koothuparamba Proj AE 2 |