Status Date Overall Project Status Project Officer Contact
08 Dec 2023 2072 HTC , 41750m pipe laid andGL tank at Arakkal colony coverslab work is in progress Koothuparamba Proj AE 2
04 Dec 2023 2065 HTC , 41500m pipe laid and cover slab of sump at GL tank at Arakkal colony coverslab work is in progress Koothuparamba Proj AE 2
28 Nov 2023 2050 HTC , 41000m pipe laid and cover slab of sump at Vengalam concrete completed Koothuparamba Proj AE 2
13 Nov 2023 2050 HTC , 40600m pipe laid and cover slab of sump at Vengalam concrete completed Koothuparamba Proj AE 2
08 Nov 2023 2025 HTC , 40000m pipe laid and pumping main of 200mm DI K9 pipe 1000 m laid. OHSR at Valiyavellicham plastering work started. Koothuparamba Proj AE 2
02 Nov 2023 2000 HTC , 40000m pipe laid and pumping main of 200mm DI K9 pipe 1000 m laid. OHSR at Valiyavellicham plastering work started. Koothuparamba Proj AE 2
02 Nov 2023 2000 HTC , 40000m pipe laid and pumping main of 200mm DI K9 pipe 1000 m laid Koothuparamba Proj AE 2
18 Oct 2023 1780 HTC given, 37000 m pipe laid. Side wall concreting of sump at Mundayod, GL tank concrete upto 1m height at Vengalam , and Kadavu colony completed. Koothuparamba Proj AE 2
11 Oct 2023 1730 HTC given, 36500 m pipe laid, Pumping main of 200mm DI K9 pipe 1000m laid, base slab concreting of sump at Mundayod colony , GL Tank at Kadavu colony , and GL Tank at Vengalam colony completed Koothuparamba Proj AE 2
05 Oct 2023 1700 HTC, 36000 m pipe laid, namboorikunnu sump cover slab completed and amarambu colony GL Tank cover slab completed Koothuparamba Proj AE 2