Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
08 Dec 2023 | 2072 HTC , 41750m pipe laid andGL tank at Arakkal colony coverslab work is in progress | Koothuparamba Proj AE 2 | |
04 Dec 2023 | 2065 HTC , 41500m pipe laid and cover slab of sump at GL tank at Arakkal colony coverslab work is in progress | Koothuparamba Proj AE 2 | |
28 Nov 2023 | 2050 HTC , 41000m pipe laid and cover slab of sump at Vengalam concrete completed | Koothuparamba Proj AE 2 | |
13 Nov 2023 | 2050 HTC , 40600m pipe laid and cover slab of sump at Vengalam concrete completed | Koothuparamba Proj AE 2 | |
08 Nov 2023 | 2025 HTC , 40000m pipe laid and pumping main of 200mm DI K9 pipe 1000 m laid. OHSR at Valiyavellicham plastering work started. | Koothuparamba Proj AE 2 | |
02 Nov 2023 | 2000 HTC , 40000m pipe laid and pumping main of 200mm DI K9 pipe 1000 m laid. OHSR at Valiyavellicham plastering work started. | Koothuparamba Proj AE 2 | |
02 Nov 2023 | 2000 HTC , 40000m pipe laid and pumping main of 200mm DI K9 pipe 1000 m laid | Koothuparamba Proj AE 2 | |
18 Oct 2023 | 1780 HTC given, 37000 m pipe laid. Side wall concreting of sump at Mundayod, GL tank concrete upto 1m height at Vengalam , and Kadavu colony completed. | Koothuparamba Proj AE 2 | |
11 Oct 2023 | 1730 HTC given, 36500 m pipe laid, Pumping main of 200mm DI K9 pipe 1000m laid, base slab concreting of sump at Mundayod colony , GL Tank at Kadavu colony , and GL Tank at Vengalam colony completed | Koothuparamba Proj AE 2 | |
05 Oct 2023 | 1700 HTC, 36000 m pipe laid, namboorikunnu sump cover slab completed and amarambu colony GL Tank cover slab completed | Koothuparamba Proj AE 2 |