Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
13 Sep 2023 | 1640 HTC, 35400 m pipe laid, retaining wall upto haunch concrete | Koothuparamba Proj AE 2 | |
05 Sep 2023 | 1590 HTC, 35400 m pipe, retaining wall upto haunch concrete | Koothuparamba Proj AE 2 | |
24 Aug 2023 | 1540 HTC, 35400m pipe, Retaining wall work at tank site | Koothuparamba Proj AE 2 | |
16 Aug 2023 | 1520 HTC completed 35400m pipe works done House connection work going on OHSR finishing work Tank: Base slab concrete done today | Koothuparamba Proj AE 2 | |
10 Aug 2023 | 1500HTC completed,35400m pipeline work done.OHSR Cover slab concrete work completed | Koothuparamba Proj AE 2 | |
03 Aug 2023 | 1470HTC completed,35300m pipeline work done.OHSR Cover slab reinforcement work completed | Koothuparamba Proj AE 2 | |
26 Jul 2023 | 1460HTC completed,35300m pipeline work done.OHSR Cover slab formwork on progress | Koothuparamba Proj AE 2 | |
19 Jul 2023 | 1450HTC completed,35300m pipeline work done.OHSR Cover slab formwork started | Koothuparamba Proj AE 2 | |
14 Jul 2023 | 1400HTC completed,35300m pipeline work done.OHSR Cover slab formwork started | Koothuparamba Proj AE 2 | |
05 Jul 2023 | 1320HTC completed,31500m pipeline work done.OHSR side wall concreting completed | Koothuparamba Proj AE 2 |