Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
12 May 2023 | 780HTC completed | Koothuparamba Proj AE 2 | |
10 May 2023 | 700 HTC completed, | Koothuparamba Proj AE 2 | |
04 May 2023 | Deck slab form work on progress and 630 HTC completed, | Koothuparamba Proj AE 2 | |
28 Apr 2023 | OHSR fourth stage column work completed,deck slab formwork started and 400HTC completed, | Koothuparamba Proj AE 2 | |
24 Apr 2023 | OHSR fourth stage column work completed and 300HTC completed, | Koothuparamba Proj AE 2 | |
18 Apr 2023 | OHSR fourth stage column work started and 280HTC completed, | Koothuparamba Proj AE 2 | |
10 Apr 2023 | OHSR fourth stage column work started and 240 HTC completed, | Koothuparamba Proj AE 2 | |
05 Apr 2023 | OHSR third stage brace beam concreting completed and 240 HTC completed, second and part bill submitted | Koothuparamba Proj AE 2 | |
30 Mar 2023 | HSR third stage column concreting completed and 225 HTC completed, second and part bill submitted | Koothuparamba Proj AE 2 | |
16 Mar 2023 | OHSR third stage column concreting completed and 200HTC completed | Koothuparamba Proj AE 2 |