Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
30 Jun 2023 | 1320HTC completed,31000m pipeline work ongoing.OHSR side wall formwork on progress | Koothuparamba Proj AE 2 | |
23 Jun 2023 | 1300HTC completed,30500m pipeline work ongoing.OHSR side wall formwork on progress | Koothuparamba Proj AE 2 | |
23 Jun 2023 | 1330HTC completed,30600m pipeline work ongoing.OHSR side wall formwork on progress | Koothuparamba Proj AE 2 | |
19 Jun 2023 | 1300HTC completed,30500m pipeline work ongoing.OHSR side wall formwork on progress | Koothuparamba Proj AE 2 | |
12 Jun 2023 | 1280HTC completed,pipeline work ongoing.OHSR work ongoing | Koothuparamba Proj AE 2 | |
06 Jun 2023 | 1250HTC completed,pipeline work ongoing.OHSR work ongoing | Koothuparamba Proj AE 2 | |
01 Jun 2023 | 1200HTC completed,pipeline work ongoing.OHSR work ongoing | Koothuparamba Proj AE 2 | |
25 May 2023 | 1130HTC completed,pipeline work ongoing.OHSR work ongoing | Koothuparamba Proj AE 2 | |
22 May 2023 | 1000HTC completed,pipeline work ongoing.OHSR work ongoing | Koothuparamba Proj AE 2 | |
18 May 2023 | 900HTC completed | Koothuparamba Proj AE 2 |