Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
27 Jun 2024 | 77500 m pipe laid , Balance work in Mooriyad cheruvanchery road (2km) is being stopped due to monsoon ban | Koothuparamba Proj AE 2 | |
22 Jun 2024 | 77500 m pipe laid , Balance work in Mooriyad cheruvanchery road (2km) is being stopped due to monsoon ban | Koothuparamba Proj AE 2 | |
19 Jun 2024 | 77500 m pipe laid , Balance work progressing in Mooriyad cheruvanchery road (2km) | Koothuparamba Proj AE 2 | |
13 Jun 2024 | 77000 m pipe laid , Balance work progressing in Mooriyad cheruvanchery road (2km) | Koothuparamba Proj AE 2 | |
07 Jun 2024 | 77000 m pipe laid , Balance work progressing in Mooriyad cheruvanchery road (2km) | Koothuparamba Proj AE 2 | |
03 Jun 2024 | 77000 m pipe laid , Balance work progressing in Mooriyad cheruvanchery road (2km) | Koothuparamba Proj AE 2 | |
29 May 2024 | Balance work progressing in Mooriyad cheruvanchery road (2km) | Koothuparamba Proj AE 2 | |
25 May 2024 | Permission availed from PWD and balance work commensed in Mooriyad cheruvanchery road (2km) | Koothuparamba Proj AE 2 | |
21 May 2024 | 350 DI pipe laying started | Koothuparamba Proj AE 2 | |
16 May 2024 | Finishing work on progress | Koothuparamba Proj AE 2 |