Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
29 Dec 2022 | 8000 m pipes are laid and columns above plinth beam for OHSR shuttering work is in progress | Koothuparamba Proj AE 2 | |
23 Dec 2022 | Plinth beam of OHSR Concrete complete and 6000 m pipe laid | Koothuparamba Proj AE 2 | |
17 Dec 2022 | Plinth beam of OHSR work in progress and 3800 m pipe laid | Koothuparamba Proj AE 2 | |
12 Dec 2022 | Column For OHSR concreted upto plinth level and 3200 m pipe laid | Koothuparamba Proj AE 2 | |
08 Dec 2022 | 2800m pipe laid | Koothuparamba Proj AE 2 | |
06 Dec 2022 | Pumphouse at Valiyavelicham roof slab concreted and 2500m pipe laid | Koothuparamba Proj AE 2 | |
29 Nov 2022 | Foundation of 5 LL OHSR is completed and 1800 m pipe laid | Koothuparamba Proj AE 2 | |
24 Nov 2022 | Reinforcement work for ohsr in progress and pipe line work started and 1000 m laid | Koothuparamba Proj AE 2 | |
19 Nov 2022 | Reinforcement work started for OHSR, Pipe laying work started | Koothuparamba Proj AE 2 | |
17 Nov 2022 | PCC for OHSR completed and Laterite work for pumphouse completed up to lintel level | Koothuparamba Proj AE 2 |