Status Date | Overall Project Status | Project Officer | Contact |
---|---|---|---|
09 Mar 2023 | OHSRthird stage column work on progress and 170HTC completed | Koothuparamba Proj AE 2 | |
02 Mar 2023 | OHSR Third stage column work on progress, and 21000m pipe laid,110 HTC completed | Koothuparamba Proj AE 2 | |
27 Feb 2023 | OHSR second stage brace beam concrete completed, and 20000 m pipe laid,96 HTC completed | Koothuparamba Proj AE 2 | |
23 Feb 2023 | OHSR brace beam form work and reinforcement work on progress and 18100 m pipe laid,83 HTC completed | Koothuparamba Proj AE 2 | |
20 Feb 2023 | OHSR brace beam form work and reinforcement work on progress and 17400 m pipe laid | Koothuparamba Proj AE 2 | |
17 Feb 2023 | OHSR brace beam form work and reinforcement started and 17200 m pipe laid | Koothuparamba Proj AE 2 | |
14 Feb 2023 | OHSR Second stage column concrete completed and form work started for brace beam and 16700 m pipe laid | Koothuparamba Proj AE 2 | |
10 Feb 2023 | OHSR First floor column work on progress and 16400m pipe laid | Koothuparamba Proj AE 2 | |
08 Feb 2023 | OHSR First floor column work on progress and 16000m pipe laid | Koothuparamba Proj AE 2 | |
04 Feb 2023 | OHSR First floor column work on progress and 15600m pipe laid | Koothuparamba Proj AE 2 |