Overall Project Status

Status Date Overall Project Status Project Officer Contact
23 Apr 2024 PHASE II – PACK 1- Work in progress | 91% Completed | 23/04/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PHASE II – PACK – 2 PART 2 - Not Started | 23/04/2024 Work not started PHASE II – PACK 3 ZONE 1 - Work in progress |85%Completed | 23/04/2024 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.500 km /out of 120km , 1.) 90 mm 6 kg-48540m supplied- 33872 m laid 2.) 90 mm 8 kg-37362m supplied and 31415 m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3811m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2520 m laid-1304.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2766.25 M laid 17) 350mm di 1407 m supplied-493.5 M PHASE II – PACK – 2 PART 1 - Work in progress | 72% Completed | 23/04/2024 WORK FORE CLOSED ON 17.05.2023 VIDE ORDER NO KWA/PHC/PKD/KIIFB/Vandazhy/ph II/PACK-II/17-18, Balance work arranged in kiifb vandazhy vadakkenchery kizhakkenchery kannambra panchayaths phase-2 pack-2 part-1 Chittur Project Dn - AE 3
11 Apr 2024 Pack-1 Work in progress | 91% Completed | 11/04/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Pack-pack-2-part2 Not Started | 11/04/2024 Work not started Pack-3 Work in progress | 83% Completed | 11/04/2024 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 100.248 km /out of 120km , 1.) 90 mm 6 kg-48540m supplied- 33872 m laid 2.) 90 mm 8 kg-37362m supplied and 31109. m laid 3.) 90mm 10 kg 240m supplied-60m 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4665.80 m laid 5) 140mm 6kg-5620 m supplied 3790.00 m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2520 m laid-1292.5 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -105 M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1713.25 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied – 831.05mlaid 16)400MM DI-2833.00m supplied -2720.25M laid 17) 350mm di 1407 m supplied-225.50 Pack-2-part-1 Work in progress | 72% Completed | 16/02/2024 WORK FORE CLOSED ON 17.05.2023 VIDE ORDER NO KWA/PHC/PKD/KIIFB/Vandazhy/ph II/PACK-II/17-18, Balance work arranged in kiifb vandazhy vadakkenchery kizhakkenchery kannambra panchayaths phase-2 pack-2 part-2 Chittur Project Dn - AE 3
16 Feb 2024 PACK-3 Work in progress | 80% Completed | 16/02/2024 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-120 km, Total laid- 96.37 km /out of 120km , 1.) 90 mm 6 kg-48540m supplied- 31850 m laid 2.) 90 mm 8 kg-37362m supplied and 30803.00 m laid 3.) 90mm 10 kg 240m supplied-laid nil 3a) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-5268 m supplied and 4107.80 m laid 5) 140mm 6kg-5620 m supplied 3346.00 m laid 6) 140mm 8 kg-1953 m supplied -1146 m laid 7) 160 mm 6 kg 2928 m supplied -3834 m laid 8) 160 mm 8 kg-1050 m supplied 1009.50m 9) 80 mm GI- 2520 m laid-1175.50 m laid 10)100 mm GI-312 m supplied-224 .50M laid 11)125mm GI-130m supplied -33.30M laid 12)150MM GI-136.50 m supplied 102M 13)450MM DI-2189 m supplied-1465.75 laidM 14)200mm DI-1977.50 m supplied -1099.75 laidM 15)250mm di-2915m supplied - 811.55mlaid 16)400MM DI-2833.00m supplied -2720.25M laid 17) 350mm di 1407 m supplied-225.50M PART2 Not Started | 16/02/2024 New estimate submitted to kiifb for approval PACK-1 Work in progress | 91% Completed | 16/02/2024 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Pack-2-part-1 Work in progress | 72% Completed | 16/02/2024 WORK FORE CLOSED ON 17.05.2023 VIDE ORDER NO KWA/PHC/PKD/KIIFB/Vandazhy/ph II/PACK-II/17-18, Balance work arranged in kiifb vandazhy vadakkenchery kizhakkenchery kannambra panchayaths phase-2 pack-2 part-2 Chittur Project Dn - AE 3
03 Nov 2023 Phase-1 Work in progress | 91% Completed | 03/11/2023 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Phase-2-pack-3 Work in progress | 60% Completed | 03/11/2023 Work in progress | 60% Completed | 12/10/2023 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid- 72.1090 km /out of 120km , 1.) 90 mm 6 kg-26km supplied- 29714 m laid 2) 90 mm 8 kg-25km supplied and 26585 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2734.00 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 1061 m laid 10)100 mm GI-224 M laid 11)125mm GI-33M 12)150MM GI-102M 13)450MM DI-1424.50M 14)200mm DI-984.50M 15)250mm di-613.55m Phase 2-prt-2- Not Started | 03/11/2023 work not started Chittur Project Dn - AE 3
12 Oct 2023 PACK-1 Work in progress | 91% Completed | 12/10/2023 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PACK-2-PART-2 Not Started | 12/10/2023 work not started PART-1 Work in progress | 72% Completed | 12/10/2023 Anchor block work,GI Pip work ,leak rectification works are in progress. And TOTAL K 113.766kM LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.567 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-175.008M 18)450MM DI -531.293M 19)400 MM DI-215.008m 20)350MM DI-206.09M . FHTC -1843 provided / out of 6480 PACK-3 Work in progress | 55% Completed | 12/10/2023 Work in progress | 67% Completed | 12/10/2023 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid- 65.039 km /out of 120km , 1.) 90 mm 6 kg-25km supplied- 25628 m laid 2) 90 mm 8 kg-25km supplied and 26585 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2734.00 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 1061 m laid 10)100 mm GI-224 M laid 11)125mm GI-33M 12)150MM GI-102M 13)450MM DI-38.50M Chittur Project Dn - AE 3
07 Sep 2023 PACK-1 Work in progress | 91% Completed | 07/09/2023 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PART-2 Not Started |07/09/2023 work not started PART-1 Work in progress | 72% Completed | 07/09/2023 Anchor block work,GI Pip work ,leak rectification works are in progress. And TOTAL K 113.766kM LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.567 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-175.008M 18)450MM DI -531.293M 19)400 MM DI-215.008m 20)350MM DI-206.09M . FHTC -1843 provided / out of 6480 PACK-3 Work in progress | 55% Completed | 07/09/2023 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km , 1.) 90 mm 6 kg-25km supplied- 25628 m laid 2) 90 mm 8 kg-25km supplied and 26585 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2734.00 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 1061 m laid 10)100 mm GI-224 M laid 11)125mm GI-33M 12)150MM GI-102M Chittur Project Dn - AE 3
26 Aug 2023 PACK-1 Work in progress | 91% Completed | 26/08/2023 OHSR colour washing work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PART-2 Not Started | 26/08/2023 work not started PART-1 Work in progress | 72% Completed | 26/08/2023 Anchor block work,GI Pip work ,leak rectification works are in progress. And TOTAL K 113.766kM LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.567 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-175.008M 18)450MM DI -531.293M 19)400 MM DI-215.008m 20)350MM DI-206.09M . FHTC -1843 provided / out of 6480 PACK-3 Work in progress | 55% Completed | 26/08/2023 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km , 1.) 90 mm 6 kg-25km supplied- 25628 m laid 2) 90 mm 8 kg-25km supplied and 26585 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2734.00 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 1061 m laid 10)100 mm GI-224 M laid 11)125mm GI-33M 12)150MM GI-102M Chittur Project Dn - AE 3
04 Aug 2023 PACK-1 Work in progress | 91% Completed | 01/08/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PACK-2 Not Started | 01/08/2023 work not started PACK-3 Work in progress | 55% Completed | 01/08/2023 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km , 1.) 90 mm 6 kg-25km supplied- 25628 m laid 2) 90 mm 8 kg-25km supplied and 26585 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2734.00 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 1061 m laid 10)100 mm GI-224 M laid 11)125mm GI-33M 12)150MM GI-102M PART-1 Work in progress | 71% Completed | 20/07/2023 Anchor block work,GI Pip work ,leak rectification works are in progress. And TOTAL K 113.698kM LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.543 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-158.508M 18)450MM DI -531.293M 19)400 MM DI-193.008m 20)350MM DI-200.59M . FHTC -1843 provided / out of 6480 Chittur Project Dn - AE 3
20 Jul 2023 PACK-1 Work in progress | 91% Completed | 20/07/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PACK-2 Not Started | 20/07/2023 work not started PACK-3 Work in progress | 55% Completed | 20/07/2023 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km , 1.) 90 mm 6 kg-25km supplied- 25628 m laid 2) 90 mm 8 kg-25km supplied and 26585 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2734.00 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 1061 m laid 10)100 mm GI-224 M laid 11)125mm GI-33M 12)150MM GI-102M PART-1 Work in progress | 71% Completed | 20/07/2023 Anchor block work,GI Pip work ,leak rectification works are in progress. And TOTAL K 113.698kM LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.543 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-158.508M 18)450MM DI -531.293M 19)400 MM DI-193.008m 20)350MM DI-200.59M . FHTC -1843 provided / out of 6480 Chittur Project Dn - AE 3
13 Jul 2023 Pack-1 Work in progress | 91% Completed OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Part-2 Not Started | 13/07/2023 work not started pack-3 Work in progress | 55% Completed | 13/07/2023 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km ,1.) 90 mm 6 kg-25km supplied- 23387.50 m laid 2) 90 mm 8 kg-25km supplied and 22866 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2568.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Pack-2-part-1 Work in progress | 71% Completed | 13/07/2023 Anchor block work,GI Pip work ,leak rectification works are in progress. And TOTAL K 113.698kM LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.543 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-158.508M 18)450MM DI -531.293M 19)400 MM DI-193.008m 20)350MM DI-200.59M . FHTC -1843 provided / out of 6480 Chittur Project Dn - AE 3