Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Jul 2023 Pack-1 Work in progress | 91% Completed OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Part-2 Not Started | 13/07/2023 work not started pack-3 Work in progress | 55% Completed | 13/07/2023 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km ,1.) 90 mm 6 kg-25km supplied- 23387.50 m laid 2) 90 mm 8 kg-25km supplied and 22866 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2568.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Pack-2-part-1 Work in progress | 71% Completed | 13/07/2023 Anchor block work,GI Pip work ,leak rectification works are in progress. And TOTAL K 113.698kM LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.543 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-158.508M 18)450MM DI -531.293M 19)400 MM DI-193.008m 20)350MM DI-200.59M . FHTC -1843 provided / out of 6480 Chittur Project Dn - AE 3
23 Jun 2023 PACK-1 Work in progress | 91% Completed | 23/06/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress PACK-2-PART-1 Work in progress | 71% Completed | 23/06/2023 Anchor block work,GI Pip work ,leak rectification works are in progress. And TOTAL K 113.655M LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.522 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-147.508.008M 18)450MM DI -531.293M 19)400 MM DI-182.008m 20)350MM DI-200.59M . FHTC -1843 provided / out of 6480 PART-2 Not Started | 23/06/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. PACK-3 Work in progress | 55% Completed | 23/06/2023 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km ,1.) 90 mm 6 kg-25km supplied- 23387.50 m laid 2) 90 mm 8 kg-25km supplied and 22866 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2568.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Chittur Project Dn - AE 3
16 Jun 2023 Part-1 Work in progress | 71% Completed | 16/06/2023 Anchor block work,GI Pip work ,leak rectification works are in progress. And TOTAL K 113.655M LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.522 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-147.508.008M 18)450MM DI -531.293M 19)400 MM DI-182.008m 20)350MM DI-200.59M . FHTC -1843 provided / out of 6480 Pack-3 Work in progress | 55% Completed | 16/06/2023 1300 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km ,1.) 90 mm 6 kg-25km supplied- 23387.50 m laid 2) 90 mm 8 kg-25km supplied and 22866 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2568.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Pack-1 Work in progress | 91% Completed | 16/06/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Part-2 Not Started | 16/06/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Chittur Project Dn - AE 3
09 Jun 2023 Part-1 Work in progress | 71% Completed | 09/06/2023 Anchor block work,GI Pip work ,leak rectification works are in progress. And TOTAL K 113.655M LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.522 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-147.508.008M 18)450MM DI -531.293M 19)400 MM DI-182.008m 20)350MM DI-200.59M . FHTC -1843 provided / out of 6480 Pack1 Work in progress | 91% Completed | 09/06/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Part-2 Not Started | 09/06/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Pack-3 Work in progress | 55% Completed | 09/06/2023 1186 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km ,1.) 90 mm 6 kg-25km supplied- 23387.50 m laid 2) 90 mm 8 kg-25km supplied and 22866 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2568.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Chittur Project Dn - AE 3
02 Jun 2023 Pack-1 Work in progress | 91% Completed | 02/06/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid,GAP filling work is in progress Part-1 Work in progress | 71% Completed | 02/06/2023 Anchor block work in progress,leak rectification works are in progress. And TOTAL K 113.655M LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.522 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-147.508.008M 18)450MM DI -531.293M 19)400 MM DI-182.008m 20)350MM DI-200.59M . FHTC -1843 provided / out of 6480 Part-2 Not Started | 02/06/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Pack-3 Work in progress | 55% Completed | 02/06/2023 1035 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km ,1.) 90 mm 6 kg-25km supplied- 23387.50 m laid 2) 90 mm 8 kg-25km supplied and 22866 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2568.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Chittur Project Dn - AE 3
26 May 2023 Pack-1 Work in progress | 90% Completed | 25/05/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 15.00KM PIPE supplied at site and 14810.20km laid, Part-1 Work in progress | 71% Completed | 25/05/2023 Anchor block work in progress,leak rectification works are in progress. And TOTAL K 113.655M LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.522 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-147.508.008M 18)450MM DI -531.293M 19)400 MM DI-182.008m 20)350MM DI-200.59M . FHTC -1843 provided / out of 6480 Pack-3 Work in progress | 55% Completed | 25/05/2023 914 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km ,1.) 90 mm 6 kg-25km supplied- 23387.50 m laid 2) 90 mm 8 kg-25km supplied and 22866 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2568.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Part-2 Not Started | 25/05/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Chittur Project Dn - AE 3
19 May 2023 PACK-1 Work in progress | 89% Completed | 19/05/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14.70KM PIPE supplied at site and 14651.90km laid, PACK-2-PART-1 Work in progress | 71% Completed | 19/05/2023 Anchor block work in progress,leak rectification works are in progress. And TOTAL K 113.655M LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.522 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-147.508.008M 18)450MM DI -531.293M 19)400 MM DI-182.008m 20)350MM DI-200.59M . FHTC -1843 provided / out of 6480 Part-2 Not Started | 19/05/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Pack-3 Work in progress | 55% Completed | 19/05/2023 Not Started | 19/05/2023 872 FHTC provided. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km ,1.) 90 mm 6 kg-25km supplied- 23387.50 m laid 2) 90 mm 8 kg-25km supplied and 22866 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2568.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Chittur Project Dn - AE 3
11 May 2023 Part-1 Work in progress | 71% Completed | 11/05/2023 leak rectification works are in progress. And TOTAL K 113.655M LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.522 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.861Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-147.508.008M 18)450MM DI -531.293M 19)400 MM DI-182.008m 20)350MM DI-200.59M . FHTC -1843 provided / out of 6480 pack-3 Work in progress | 55% Completed | 11/05/2023 FHTC work in prohress. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km ,FHTC-581 Nos provided 1.) 90 mm 6 kg-25km supplied- 23387.50 m laid 2) 90 mm 8 kg-25km supplied and 22866 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2568.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Pack-1 Work in progress | 89% Completed | 11/05/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14431.90km laid, Part-2 Work not started Chittur Project Dn - AE 3
28 Apr 2023 Pack-1 Work in progress | 88% Completed | 28/04/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14341.70 km laid, Pack-2-part-1 Work in progress | 71% Completed | 28/04/2023 leak rectification works are in progress. And TOTAL K 113.345M LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.324 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-144.008M 18)450MM DI -489.4935M 19)400 MM DI-144.008m 20)350MM DI-189.4935M pack-3 Work in progress | 54% Completed | 28/04/2023 FHTC work in prohress. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km ,FHTC-289 Nos provided 1.) 90 mm 6 kg-25km supplied- 23387.50 m laid 2) 90 mm 8 kg-25km supplied and 22866 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2568.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Part-2 Not Started | 28/04/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Chittur Project Dn - AE 3
24 Apr 2023 PACK-1 Work in progress | 88% Completed | 24/04/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14.165 km laid, PART-1 Work in progress | 70% Completed | 24/04/2023 leak rectification works are in progress. And TOTAL K 113.222M LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.324 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-82.508M 18)450MM DI -489.4935M 19)400 MM DI-82.508M 20)350MM DI-189.4935M PACK-3 Work in progress | 54% Completed | 24/04/2023 FHTC work in prohress. Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km ,FHTC-180 Nos provided 1.) 90 mm 6 kg-25km supplied- 23387.50 m laid 2) 90 mm 8 kg-25km supplied and 22866 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2568.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M PART-2 Not Started | 24/04/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Chittur Project Dn - AE 3