Overall Project Status

Status Date Overall Project Status Project Officer Contact
11 Apr 2023 Pack-III Work in progress | 54% Completed | 11/04/2023 Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-65.001 km /out of 120km ,FHTC-180 Nos provided 1.) 90 mm 6 kg-25km supplied- 23387.50 m laid 2) 90 mm 8 kg-25km supplied and 22866 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2568.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M PART-1 Work in progress | 70% Completed | 11/04/2023 leak rectification works are in progress. And TOTAL K 112.935M LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.24 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-82.50M 18)450MM DI -489.40M 19)400 MM DI-82.50M 20)350MM DI-189.40M PART-2 Not Started | 11/04/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. PACK-1 Work in progress | 88% Completed | 11/04/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14.16 km laid, Chittur Project Dn - AE 3
06 Apr 2023 PACK-1 Work in progress | 88% Completed | 06/04/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14.16 km laid, PACK-3 Work in progress | 53% Completed | 06/04/2023 Various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km, Total laid-63.954 km /out of 120km 1.) 90 mm 6 kg-22890m supplied- 22826.50 m laid 2) 90 mm 8 kg-15600m supplied and 22380 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2568.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M PART-2 Not Started | 06/04/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Pack-3-part-1 Work in progress | 70% Completed | 06/04/2023 leak rectification works are in progress. And TOTAL K 112.805M LAID/OUT OF 160KM 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-55.192 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M 17)500MM DI K9-82.50M 18)450MM DI -148.50M 19)400 MM DI-82.50M 20)350MM DI-148.50M Chittur Project Dn - AE 3
24 Mar 2023 Pack-1 Work in progress | 85% Completed | 24/03/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14.0771 km laid, Pack-3 Work in progress | 52% Completed | 24/03/2023 various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km , Total laid-62.913 km /out of 120km 1.) 90 mm 6 kg-22890m supplied- 21791.50 m laid 2) 90 mm 8 kg-15600m supplied and 22380 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2562.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M part-1 Work in progress | 67% Completed | 24/03/2023 leak rectification works are in progress. And TOTAL K 111.9715M LAID 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-54.820 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M part-2 Not Started | 24/03/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Chittur Project Dn - AE 3
13 Mar 2023 Pack-1 Work in progress | 85% Completed | 13/03/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14.0771 km laid, Pack-3 Work in progress | 52% Completed | 13/03/2023 various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km , Total laid-62.913 km /out of 120km 1.) 90 mm 6 kg-22890m supplied- 21791.50 m laid 2) 90 mm 8 kg-15600m supplied and 22380 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2562.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M part-1 Work in progress | 67% Completed | 13/03/2023 leak rectification works are in progress. And TOTAL K 111.9715M LAID 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-54.820 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M part-2 Not Started | 13/03/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Chittur Project Dn - AE 3
05 Mar 2023 Pack-1 Work in progress | 85% Completed | 05/03/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14.0771 km laid, Pack-2part-1 Work in progress | 67% Completed | 05/03/2023 leak rectification works are in progress. And TOTAL 111.933 KM LAID 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-54.820 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M part-2 Not Started | 05/03/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Pack-3 Work in progress | 52% Completed | 05/03/2023 various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km , Total laid-61.917 km /out of 120km 1.) 90 mm 6 kg-22890m supplied- 21791.50 m laid 2) 90 mm 8 kg-15600m supplied and 21384 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2562.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Chittur Project Dn - AE 3
24 Feb 2023 Pack-1 Work in progress | 83% Completed | 24/02/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14.0771 km laid, Pack2-part-1 Work in progress | 67% Completed | 24/02/2023 leak rectification works are in progress. And TOTAL 111.933 KM LAID 1.) 90 mm pvc -8 kg 28.233 km laid 2.) 90mm pvc-6 kg-54.820 KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.365Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M pack-2-part-2 Not Started | 24/02/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Pack-3 Work in progress | 50% Completed | 24/02/2023 various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km , Total laid-61.917 km /out of 120km 1.) 90 mm 6 kg-22890m supplied- 21791.50 m laid 2) 90 mm 8 kg-15600m supplied and 21384 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2562.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Chittur Project Dn - AE 3
17 Feb 2023 Pack-1 Work in progress | 83% Completed | 17/02/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14.0771 km laid, Part-1 Work in progress | 67% Completed | 17/02/2023 leak rectification works are in progress. and TOTAL 110.637 KM LAID 1.) 90 mm pvc -8 kg 27.039 km laid 2.) 90mm pvc-6 kg-54.718KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.364Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M part2 Not Started | 17/02/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Pack-3 Work in progress | 50% Completed | 17/02/2023 various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km , Total laid-60.621 km /out of 120km 1.) 90 mm 6 kg-22890m supplied- 21689.50 m laid 2) 90 mm 8 kg-15600m supplied and 20190.00 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2562.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Chittur Project Dn - AE 3
10 Feb 2023 Pack-1 Work in progress | 83% Completed | 10/02/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14.0771 km laid, Part-1 Work in progress | 67% Completed | 10/02/2023 leak rectification works are in progress. and TOTAL 110.637 KM LAID 1.) 90 mm pvc -8 kg 27.039 km laid 2.) 90mm pvc-6 kg-54.718KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.364Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M part2 Not Started | 10/02/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Pack-3 Work in progress | 50% Completed | 10/02/2023 various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km , Total laid-60.621 km /out of 120km 1.) 90 mm 6 kg-22890m supplied- 21689.50 m laid 2) 90 mm 8 kg-15600m supplied and 20190.00 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2562.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 850.70 m laid 10)100 mm GI-211.60 M laid 11)125mm GI-33M 12)150MM GI-30M Chittur Project Dn - AE 3
03 Feb 2023 PACK-1 Work in progress | 82% Completed | 02/02/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14.0771 km laid, Part-2 Not Started | 03/02/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Pack-3 Work in progress | 47% Completed | 03/02/2023 various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km , Total laid-58.010 km 1.) 90 mm 6 kg-22890m supplied- 20111.50 m laid 2) 90 mm 8 kg-15600m supplied and 19242.00 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2562.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 811.70 m laid 10)100 mm GI-165.50 M laid 11)125mm GI-33M 12)150MM GI-30M part-1 Work in progress | 67% Completed | 02/02/2023 GI pipe/pvc pipe linking works are in progress. and TOTAL 110.637 KM LAID 1.) 90 mm pvc -8 kg 27.039 km laid 2.) 90mm pvc-6 kg-54.718KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.364Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M Chittur Project Dn - AE 3
02 Feb 2023 Pack-1 Work in progress | 82% Completed | 02/02/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14.0771 km laid pack-3 Work in progress | 47% Completed | 02/02/2023 various dia of pvc pipes and GI pipes are supplied at site Total supply-110 km , Total laid-58.010 km 1.) 90 mm 6 kg-22890m supplied- 20111.50 m laid 2) 90 mm 8 kg-15600m supplied and 19242.00 m laid 3) 110mm 6 kg-4278m supplied and 2966 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2562.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2844 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 811.70 m laid 10)100 mm GI-165.50 M laid 11)125mm GI-33M 12)150MM GI-30M part-2 Not Started | 02/02/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Part-1 Work in progress | 67% Completed | 02/02/2023 GI pipe/pvc pipe linking works are in progress. and TOTAL 110.637 KM LAID 1.) 90 mm pvc -8 kg 27.039 km laid 2.) 90mm pvc-6 kg-54.718KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.364Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M Chittur Project Dn - AE 3