Status Date |
Overall Project Status |
Project Officer |
Contact |
12 Dec 2021 |
Pack-1
Work in progress | 51% Completed | 12/12/2021
floor beam and slab concrete work completed and side wall reinforcement work in progress
part-1
Work in progress | 36% Completed | 12/12/2021
1.) 90 mm pvc -8 kg 19.216 m laid 2.) 90mm pvc-6 kg-32.225KM laid 3.) 110 mm pvc 8 kg- 1.908 m laid 4.)110mm pvc -6kg-4.258Km laid 5.)140mm pvc-6kg-1.314Km 6). 160mm pvc-6kg-1.128Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.089KM laid 10).250mm DI pipe-0.5314Km Rider main 90mm 6 kg-1.75 m laid Total 65.536km laid
Part-2
Not Started | 12/12/2021
revised estimate prepared and submitted for approval
pack-3
Not Started | 12/12/2021
work not started
|
Chittur Project Dn - AE 3 |
|
05 Dec 2021 |
Pack-2-part-1
Work in progress | 36% Completed | 05/12/2021
1.) 90 mm pvc -8 kg 17.344 m laid 2.) 90mm pvc-6 kg-30.931KM laid 3.) 110 mm pvc 8 kg- 1.908 m laid 4.)110mm pvc -6kg-3.862Km laid 5.)140mm pvc-6kg-1.314Km 6). 160mm pvc-6kg-1.128Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.089KM laid 10).250mm DI pipe-0.5314Km Rider main 90mm 6 kg-1.75 m laid Total 61.974km laid
Phase-2-pack-1
Work in progress | 51% Completed | 05/12/2021
floor beam and slab concrete work completed and side wall reinforcement work in progress
pack-2-part-2
Not Started | 05/12/2021
revised estimate prepared and submitted for approval
pack-3
Not Started | 05/12/2021
Agreement to be executed
|
Chittur Project Dn - AE 3 |
|
28 Nov 2021 |
Pack-1
Work in progress | 49% Completed | 28/11/2021
floor beam and slab concrete work in progress ,
ph-2-pack-3
Not Started | 28/11/2021
Agreement to be executed
Pack-2-part-1
Work in progress | 36% Completed | 28/11/2021
1.) 90 mm pvc -8 kg 17.344 m laid 2.) 90mm pvc-6 kg-30.931KM laid 3.) 110 mm pvc 8 kg- 1.908 m laid 4.)110mm pvc -6kg-3.862Km laid 5.)140mm pvc-6kg-1.314Km 6). 160mm pvc-6kg-1.128Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.089KM laid 10).250mm DI pipe-0.5314Km Rider main 90mm 6 kg-1.75 m laid Total 60.974km laid
Pack-2-part-2
Not Started | 28/11/2021
The work has been cancelled,Revised estimate under preparation
|
Chittur Project Dn - AE 3 |
|
21 Nov 2021 |
Pack-1
floor beam and slab shuttering and reinforcement work in progress ,
pack-2-part-2
Not Started | 21/11/2021
The work has been cancelled,Revised estimate under preparation
Pack-2-part-1
Work in progress | 36% Completed | 21/11/2021
1.) 90 mm pvc -8 kg 17.092m laid 2.) 90mm pvc-6 kg-29.113KM laid 3.) 110 mm pvc 8 kg-1.566 m laid 4.)110mm pvc -6kg-3.862Km laid 5.)140mm pvc-6kg-1.176Km 6). 160mm pvc-6kg-1.128Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.056KM laid 10).250mm DI pipe-0.4424Km Rider main 90mm 6 kg-1.674 m laid Total 59.00km laid
Pack-3
Not Started | 21/11/2021
Agreement to be executed ,
|
Chittur Project Dn - AE 3 |
|
14 Nov 2021 |
pack-1
Work in progress | 47% Completed | 14/11/2021
floor beam and slab shuttering and reinforcement work in progress ,
pack-2-part-2
Not Started | 14/11/2021
Prequalification process to be done
Pack-3
Not Started | 14/11/2021
Agreement to be executed ,
Pack-2-part-1
Work in progress | 36% Completed | 14/11/2021
Total 59.802km laid 1.) 90 mm pvc -8 kg 17032.50m laid 2.) 90mm pvc-6 kg-27333.00m laid 3.) 110 mm pvc 8 kg-1530.00 m laid 4.)110mm pvc -6kg-2776.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid
|
Chittur Project Dn - AE 3 |
|
07 Nov 2021 |
Pack-1- Work in progress | 47% Completed | 07/11/2021
floor beam and slab shuttering and reinforcement work in progress ,
pack-2-part-1
Work in progress | 36% Completed | 07/11/2021
Total 59.802km laid 1.) 90 mm pvc -8 kg 17032.50m laid 2.) 90mm pvc-6 kg-27333.00m laid 3.) 110 mm pvc 8 kg-1530.00 m laid 4.)110mm pvc -6kg-2776.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid
Pack-3
Not Started | 07/11/2021
Agreement to be executed ,
Pack-2-part-2 -Not Started | 07/11/2021
Prequalification process to be done
|
Chittur Project Dn - AE 3 |
|
31 Oct 2021 |
pack-1
Work in progress | 46% Completed | 31/10/2021
floor beam and slab shuttering and reinforcement work in progress ,
pack-iii
Not Started | 31/10/2021
Agreement to be executed ,
Pack-2-part-2
Not Started | 31/10/2021
Prequalification process to be done
Part-1
Work in progress | 35% Completed | 31/10/2021
Total 59.802km laid 1.) 90 mm pvc -8 kg 17032.50m laid 2.) 90mm pvc-6 kg-27333.00m laid 3.) 110 mm pvc 8 kg-1530.00 m laid 4.)110mm pvc -6kg-2776.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid
|
Chittur Project Dn - AE 3 |
|
24 Oct 2021 |
Pack-2-part-1
Work in progress | 34% Completed | 24/10/2021
Total 58.802km laid 1.) 90 mm pvc -8 kg 17032.50m laid 2.) 90mm pvc-6 kg-27333.00m laid 3.) 110 mm pvc 8 kg-1530.00 m laid 4.)110mm pvc -6kg-2776.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid
Pack-1
Work in progress | 46% Completed | 24/10/2021
floor beam and slab shuttering and reinforcement work in progress ,
pack-3
Not Started | 24/10/2021
Agreement to be executed ,
Pack-2-part-2
Not Started | 24/10/2021
Prequalification process to be done
|
Chittur Project Dn - AE 3 |
|
17 Oct 2021 |
Pack-2-part-1
Work in progress | 33% Completed | 17/10/2021
Total 57.802km laid 1.) 90 mm pvc -8 kg 16804.50m laid 2.) 90mm pvc-6 kg-27228.00 m laid 3.) 110 mm pvc 8 kg-1314.00 m laid 4.)110mm pvc -6kg-2662.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid
Pack-2part-2
Not Started | 17/10/2021
Prequalification process to be done
Pack-1
Work in progress | 46% Completed | 17/10/2021
floor beam and slab shuttering and reinforcement work in progress
pack-3
Not Started | 17/10/2021
Agreement to be executed ,
|
Chittur Project Dn - AE 3 |
|
10 Oct 2021 |
Pack-1
Work in progress | 46% Completed | 10/10/2021
floor beam and slab shuttering and reinforcement work in progress
pack-2-part-1
Work in progress | 33% Completed | 10/10/2021
Total 55.802km laid 1.) 90 mm pvc -8 kg 16804.50m laid 2.) 90mm pvc-6 kg-27228.00 m laid 3.) 110 mm pvc 8 kg-1314.00 m laid 4.)110mm pvc -6kg-2662.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid
Pack-2-part-2
Not Started | 10/10/2021
Prequalification process to be done
Pack-3
Not Started | 10/10/2021
Agreement to be executed ,
|
Chittur Project Dn - AE 3 |
|