Overall Project Status

Status Date Overall Project Status Project Officer Contact
12 Dec 2021 Pack-1 Work in progress | 51% Completed | 12/12/2021 floor beam and slab concrete work completed and side wall reinforcement work in progress part-1 Work in progress | 36% Completed | 12/12/2021 1.) 90 mm pvc -8 kg 19.216 m laid 2.) 90mm pvc-6 kg-32.225KM laid 3.) 110 mm pvc 8 kg- 1.908 m laid 4.)110mm pvc -6kg-4.258Km laid 5.)140mm pvc-6kg-1.314Km 6). 160mm pvc-6kg-1.128Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.089KM laid 10).250mm DI pipe-0.5314Km Rider main 90mm 6 kg-1.75 m laid Total 65.536km laid Part-2 Not Started | 12/12/2021 revised estimate prepared and submitted for approval pack-3 Not Started | 12/12/2021 work not started Chittur Project Dn - AE 3
05 Dec 2021 Pack-2-part-1 Work in progress | 36% Completed | 05/12/2021 1.) 90 mm pvc -8 kg 17.344 m laid 2.) 90mm pvc-6 kg-30.931KM laid 3.) 110 mm pvc 8 kg- 1.908 m laid 4.)110mm pvc -6kg-3.862Km laid 5.)140mm pvc-6kg-1.314Km 6). 160mm pvc-6kg-1.128Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.089KM laid 10).250mm DI pipe-0.5314Km Rider main 90mm 6 kg-1.75 m laid Total 61.974km laid Phase-2-pack-1 Work in progress | 51% Completed | 05/12/2021 floor beam and slab concrete work completed and side wall reinforcement work in progress pack-2-part-2 Not Started | 05/12/2021 revised estimate prepared and submitted for approval pack-3 Not Started | 05/12/2021 Agreement to be executed Chittur Project Dn - AE 3
28 Nov 2021 Pack-1 Work in progress | 49% Completed | 28/11/2021 floor beam and slab concrete work in progress , ph-2-pack-3 Not Started | 28/11/2021 Agreement to be executed Pack-2-part-1 Work in progress | 36% Completed | 28/11/2021 1.) 90 mm pvc -8 kg 17.344 m laid 2.) 90mm pvc-6 kg-30.931KM laid 3.) 110 mm pvc 8 kg- 1.908 m laid 4.)110mm pvc -6kg-3.862Km laid 5.)140mm pvc-6kg-1.314Km 6). 160mm pvc-6kg-1.128Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.089KM laid 10).250mm DI pipe-0.5314Km Rider main 90mm 6 kg-1.75 m laid Total 60.974km laid Pack-2-part-2 Not Started | 28/11/2021 The work has been cancelled,Revised estimate under preparation Chittur Project Dn - AE 3
21 Nov 2021 Pack-1 floor beam and slab shuttering and reinforcement work in progress , pack-2-part-2 Not Started | 21/11/2021 The work has been cancelled,Revised estimate under preparation Pack-2-part-1 Work in progress | 36% Completed | 21/11/2021 1.) 90 mm pvc -8 kg 17.092m laid 2.) 90mm pvc-6 kg-29.113KM laid 3.) 110 mm pvc 8 kg-1.566 m laid 4.)110mm pvc -6kg-3.862Km laid 5.)140mm pvc-6kg-1.176Km 6). 160mm pvc-6kg-1.128Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.056KM laid 10).250mm DI pipe-0.4424Km Rider main 90mm 6 kg-1.674 m laid Total 59.00km laid Pack-3 Not Started | 21/11/2021 Agreement to be executed , Chittur Project Dn - AE 3
14 Nov 2021 pack-1 Work in progress | 47% Completed | 14/11/2021 floor beam and slab shuttering and reinforcement work in progress , pack-2-part-2 Not Started | 14/11/2021 Prequalification process to be done Pack-3 Not Started | 14/11/2021 Agreement to be executed , Pack-2-part-1 Work in progress | 36% Completed | 14/11/2021 Total 59.802km laid 1.) 90 mm pvc -8 kg 17032.50m laid 2.) 90mm pvc-6 kg-27333.00m laid 3.) 110 mm pvc 8 kg-1530.00 m laid 4.)110mm pvc -6kg-2776.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid Chittur Project Dn - AE 3
07 Nov 2021 Pack-1- Work in progress | 47% Completed | 07/11/2021 floor beam and slab shuttering and reinforcement work in progress , pack-2-part-1 Work in progress | 36% Completed | 07/11/2021 Total 59.802km laid 1.) 90 mm pvc -8 kg 17032.50m laid 2.) 90mm pvc-6 kg-27333.00m laid 3.) 110 mm pvc 8 kg-1530.00 m laid 4.)110mm pvc -6kg-2776.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid Pack-3 Not Started | 07/11/2021 Agreement to be executed , Pack-2-part-2 -Not Started | 07/11/2021 Prequalification process to be done Chittur Project Dn - AE 3
31 Oct 2021 pack-1 Work in progress | 46% Completed | 31/10/2021 floor beam and slab shuttering and reinforcement work in progress , pack-iii Not Started | 31/10/2021 Agreement to be executed , Pack-2-part-2 Not Started | 31/10/2021 Prequalification process to be done Part-1 Work in progress | 35% Completed | 31/10/2021 Total 59.802km laid 1.) 90 mm pvc -8 kg 17032.50m laid 2.) 90mm pvc-6 kg-27333.00m laid 3.) 110 mm pvc 8 kg-1530.00 m laid 4.)110mm pvc -6kg-2776.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid Chittur Project Dn - AE 3
24 Oct 2021 Pack-2-part-1 Work in progress | 34% Completed | 24/10/2021 Total 58.802km laid 1.) 90 mm pvc -8 kg 17032.50m laid 2.) 90mm pvc-6 kg-27333.00m laid 3.) 110 mm pvc 8 kg-1530.00 m laid 4.)110mm pvc -6kg-2776.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid Pack-1 Work in progress | 46% Completed | 24/10/2021 floor beam and slab shuttering and reinforcement work in progress , pack-3 Not Started | 24/10/2021 Agreement to be executed , Pack-2-part-2 Not Started | 24/10/2021 Prequalification process to be done Chittur Project Dn - AE 3
17 Oct 2021 Pack-2-part-1 Work in progress | 33% Completed | 17/10/2021 Total 57.802km laid 1.) 90 mm pvc -8 kg 16804.50m laid 2.) 90mm pvc-6 kg-27228.00 m laid 3.) 110 mm pvc 8 kg-1314.00 m laid 4.)110mm pvc -6kg-2662.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid Pack-2part-2 Not Started | 17/10/2021 Prequalification process to be done Pack-1 Work in progress | 46% Completed | 17/10/2021 floor beam and slab shuttering and reinforcement work in progress pack-3 Not Started | 17/10/2021 Agreement to be executed , Chittur Project Dn - AE 3
10 Oct 2021 Pack-1 Work in progress | 46% Completed | 10/10/2021 floor beam and slab shuttering and reinforcement work in progress pack-2-part-1 Work in progress | 33% Completed | 10/10/2021 Total 55.802km laid 1.) 90 mm pvc -8 kg 16804.50m laid 2.) 90mm pvc-6 kg-27228.00 m laid 3.) 110 mm pvc 8 kg-1314.00 m laid 4.)110mm pvc -6kg-2662.00m laid 5.)140mm pvc-6kg-1176.00m 6). 160mm pvc-6kg-1128.00m laid 7).160mm pvc -8kg-571.50m laid 8).300 MM di k9-518.50m laid 9). 200mm DI K9-809.00m laid 10).250mm DI pipe-313.50m Rider main 90mm 6 kg-1277.00 m laid Pack-2-part-2 Not Started | 10/10/2021 Prequalification process to be done Pack-3 Not Started | 10/10/2021 Agreement to be executed , Chittur Project Dn - AE 3