Overall Project Status

Status Date Overall Project Status Project Officer Contact
21 Aug 2022 Part-1 Work in progress | 64% Completed | 21/08/2022 GI pipe/pvc pipe linking works are in progress. and TOTAL 100.837KM LAID 1.) 90 mm pvc -8 kg 26.695 km laid 2.) 90mm pvc-6 kg-54.424 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.202 km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.132km Part-II Not Started | 21/08/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-I Work in progress | 67% Completed | 21/08/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, OHSR-Staircase 5th flight concrete work completed PACK-3 Work in progress | 12% Completed | 21/08/2022 Work started on 07.07.2022. DI pipes and pvc pipes various dia are supplied in site Total supply-52.764km Total laid-6.158km 1.) 90 mm 6 kg-22890m supplied-3351.50m laid 2)90 mm 8 kg-15366m supplied 3) 110mm 6 kg-4278m supplied and 1239m laid 4)110mm 8kg-3150m supplied and 795.00m laid 5)140mm 6kg-3540 m supplied 1135.50 m laid 6)160 mm 6 kg 2490 m supplied 7) 160 mm 8 kg-1050 m supplied Chittur Project Dn - AE 3
15 Aug 2022 Package-1 Work in progress | 67% Completed | 15/08/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, OHSR-Staircase 5th flight concrete work completed Pack-3 Work in progress | 10% Completed | 15/08/2022Work started on 07.07.2022. DI pipes and pvc pipes various dia are supplied in site And 1773 laid 1.) 90 mm 6 -22890m supplied-972 m laid 2)90 mm 8 kg-15366m supplied 3) 110mm 6 kg-4278m supplied and 6m 4)110mm 8kg-3150m supplied and 795.00m laid 5)140mm 6kg-3540 m supplied 6)160 mm 6 kg 2490 m supplied 7) 160 mm 8 kg-1050 m supplied Part-2 Started | 15/08/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Part-1 Work in progress | 62% Completed | 15/08/2022 TOTAL 100.563KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.395 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 0. 983km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.132km Chittur Project Dn - AE 3
09 Aug 2022 Package-1 Work in progress | 67% Completed | 09/08/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, OHSR-Staircase 5th flight concrete work completed Pack-3 Work in progress | 10% Completed | 09/08/2022Work started on 07.07.2022. DI pipes and pvc pipes various dia are supplied in site And 1773 laid 1.) 90 mm 6 -22890m supplied-972 m laid 2)90 mm 8 kg-15366m supplied 3) 110mm 6 kg-4278m supplied and 6m 4)110mm 8kg-3150m supplied and 795.00m laid 5)140mm 6kg-3540 m supplied 6)160 mm 6 kg 2490 m supplied 7) 160 mm 8 kg-1050 m supplied Part-2 Started | 09/08/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Part-1 Work in progress | 62% Completed | 09/08/2022 TOTAL 100.563KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.395 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 0. 983km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.132km Chittur Project Dn - AE 3
31 Jul 2022 Package-1 Work in progress | 67% Completed | 31/07/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, OHSR-Staircase 5th flight concrete work completed Pack-3 Work in progress | 10% Completed | 31/07/2022 Work started on 07.07.2022. DI pipes and pvc pipes various dia are supplied in site And 1773 laid 1.) 90 mm 6 -22890m supplied-972 m laid 2)90 mm 8 kg-15366m supplied 3) 110mm 6 kg-4278m supplied and 6m 4)110mm 8kg-3150m supplied and 795.00m laid 5)140mm 6kg-3540 m supplied 6)160 mm 6 kg 2490 m supplied 7) 160 mm 8 kg-1050 m supplied Part-2 Started | 31/07/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Part-1 Work in progress | 62% Completed | 31/07/2022 TOTAL 100.563KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.395 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 0. 983km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.132km Chittur Project Dn - AE 3
24 Jul 2022 Pack-2-part-2 Not Started | 24/07/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-1 Work in progress | 65% Completed | 24/07/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, OHSR-Staircase 5th flight concrete work completed Pack-3 Work in progress | 8% Completed | 24/07/2022 Work started on 07.07.2022. DI pipes and pvc pipes various dia are supplied in site And 1773 laid 1.) 90 mm 6 kg-22890m supplied-972 m laid 2)90 mm 8 kg-15366m supplied 3) 110mm 6 kg-4278m supplied and 6m 4)110mm 8kg-3150m supplied and 795.00m laid 5)140mm 6kg-3540 m supplied 6)160 mm 6 kg 2490 m supplied 7) 160 mm 8 kg-1050 m supplied Part-1 Work in progress | 62% Completed | 24/07/2022 TOTAL 100.563KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.395 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 0. 983km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.132km Chittur Project Dn - AE 3
19 Jul 2022 Pack-2-part-2 Not Started | 19/07/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-1 Work in progress | 65% Completed | 19/07/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, OHSR-Staircase 5th flight concrete work completed Pack-3 Work in progress | 8% Completed | 19/07/2022 Work started on 07.07.2022. DI pipes and pvc pipes various dia are supplied in site And 1773 laid 1.) 90 mm 6 kg-22890m supplied-972 m laid 2)90 mm 8 kg-15366m supplied 3) 110mm 6 kg-4278m supplied and 6m 4)110mm 8kg-3150m supplied and 795.00m laid 5)140mm 6kg-3540 m supplied 6)160 mm 6 kg 2490 m supplied 7) 160 mm 8 kg-1050 m supplied Part-1 Work in progress | 62% Completed | 19/07/2022 TOTAL 100.563KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.395 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 0. 983km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.132km Chittur Project Dn - AE 3
15 Jul 2022 Pack-1 Work in progress | 65% Completed | 15/07/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, OHSR-Staircase 5th flight concrete work Part-1 Work in progress | 61% Completed | 15/07/2022 TOTAL 100.528KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.395 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80mm GI-0.974km Rider main 90mm 6 kg-1.803 km laid ,13)100 mm GI-0.156km , 14) 150mm GI-0.132km Pack-3 Work in progress | 8% Completed | 15/07/2022 Work started on 07.07.2022. DI pipes and pvc pipes various dia are supplied in site and 90 mm 6kg pvc pipe-642m laid at site 1.) 90 mm 6 kg-22890m supplied-260 m laid 2)90 mm 8 kg-15366m supplied 3) 110mm 6 kg-4278m supplied 4)110mm 8kg-3150m supplied 5)140mm 6kg-3540 m supplied 6)160 mm 6 kg 2490 m supplied 7) 160 mm 8 kg-1050 m supplied Pack-2-part-2 Not Started | 15/07/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Chittur Project Dn - AE 3
11 Jul 2022 Pack-1 Work in progress | 65% Completed | 11/07/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479 KM PIPE LAID Pack-3 Work in progress | 7% Completed | 11/07/2022 Total 52.764 km pipe supplied work started on 07.07.2022. DI pipes and pvc pipes various dia are supplied in site and 90 mm 6kg pvc pipe-260m laid at site 1.) 90 mm 6 kg-22890m supplied-260 m laid 2)90 mm 8 kg-15366m supplied 3) 110mm 6 kg-4278m supplied 4)110mm 8kg-3150m supplied 5)140mm 6kg-3540 m supplied 6)160 mm 6 kg 2490 m supplied 7) 160 mm 8 kg-1050 m supplied PART-I Work in progress | 61% Completed | 11/07/2022 TOTAL 100.528KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.395 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80mm GI-0.974km Rider main 90mm 6 kg-1.803 km laid ,13)100 mm GI-0.156km , 14) 150mm GI-0.132km Part-II Not Started | 11/07/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Chittur Project Dn - AE 3
10 Jul 2022 Pack-1 Work in progress | 65% Completed | 10/07/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479 KM PIPE LAID Pack-3 Work in progress | 6% Completed | 10/07/2022 Total 52.764 km pipe supplied work started on 07.07.2022. DI pipes and pvc pipes various dia are supplied in site and 90 mm 6kg pvc pipe-260m laid at site 1.) 90 mm 6 kg-22890m supplied-260 m laid 2)90 mm 8 kg-15366m supplied 3) 110mm 6 kg-4278m supplied 4)110mm 8kg-3150m supplied 5)140mm 6kg-3540 m supplied 6)160 mm 6 kg 2490 m supplied 7) 160 mm 8 kg-1050 m supplied PART-I Work in progress | 60% Completed | 10/07/2022 TOTAL 100.528KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.341 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80mm GI-0.929km Rider main 90mm 6 kg-1.803 km laid ,13)100 mm GI-0.156km , 14) 150mm GI-0.033km Part-II Not Started | 10/07/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Chittur Project Dn - AE 3
09 Jul 2022 Pack-I -Work in progress | 60% Completed | 09/07/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479 KM PIPE LAID Pack-III Work in progress | 2% Completed | 09/07/2022 work started on 07.07.2022. DI pipes and pvc pipes various dia are supplied in site and 90 mm 6kg pvc pipe-250m laid at site pack-2- work not started Not Started | 09/07/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Part-1 Work in progress | 60% Completed | 09/07/2022 TOTAL 100.528KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.341 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80mm GI-0.929km Rider main 90mm 6 kg-1.803 km laid ,13)100 mm GI-0.156km , 14) 150mm GI-0.033km Chittur Project Dn - AE 3