Overall Project Status

Status Date Overall Project Status Project Officer Contact
06 Jul 2022 Ph-2-Pack-1 Work in progress | 57% Completed | 06/07/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress,350mm DI work-9.479 km laid Pack-2-Part-1 Work in progress | 60% Completed | 06/07/2022 TOTAL 100.528KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.341 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80mm GI-0.929km Rider main 90mm 6 kg-1.803 km laid ,13)100 mm GI-0.156km , 14) 150mm GI-0.033km Pack-2-part-2 Not Started |06/07/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-3 Not Started | 06/07/2022 Agreement executed, some DI pipes supplied at site Chittur Project Dn - AE 3
27 Jun 2022 Ph-2-Pack-1 Work in progress | 57% Completed | 27/06/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress,350mm DI work-9.479 km laid Pack-2-Part-1 Work in progress | 60% Completed | 27/06/2022 TOTAL 100.528KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.341 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80mm GI-0.929km Rider main 90mm 6 kg-1.803 km laid ,13)100 mm GI-0.156km , 14) 150mm GI-0.033km Pack-2-part-2 Not Started | 27/06/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-3 Not Started | 27/06/2022 Agreement executed, some DI pipes supplied at site Chittur Project Dn - AE 3
20 Jun 2022 Ph-2-Pack-1 Work in progress | 57% Completed | 20/06/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress,350mm DI work-9.479 km laid Pack-2-Part-1 Work in progress | 60% Completed | 20/06/2022 TOTAL 100.528KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.341 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80mm GI-0.929km Rider main 90mm 6 kg-1.803 km laid ,13)100 mm GI-0.156km , 14) 150mm GI-0.033km Pack-2-part-2 Not Started | 20/06/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-3 Not Started | 20/06/2022 Agreement executed, some DI pipes supplied at site Chittur Project Dn - AE 3
31 May 2022 Part-1 Work in progress | 60% Completed | 31/05/2022 TOTAL 100.457KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.341 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.555 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80mm GI-0.850km Rider main 90mm 6 kg-1.799 km laid ,13)100 mm GI-0.156km , 14) 150mm GI-0.018km Part-2 Not Started | 17/05/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-1 Work in progress | 56% Completed | 17/05/2022 OHSR-Sidewall second lift concrete work complete and balance work in progress,350mm DI work-9.479 km laid Pack-3 Agreement executed Chittur Project Dn - AE 3
23 May 2022 Part-1 Work in progress | 60% Completed | 23/05/2022 TOTAL 100.457KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.341 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.555 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80mm GI-0.850km Rider main 90mm 6 kg-1.799 km laid ,13)100 mm GI-0.156km , 14) 150mm GI-0.018km Part-2 Not Started | 17/05/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-1 Work in progress | 56% Completed | 17/05/2022 OHSR-Sidewall second lift concrete work complete and balance work in progress,350mm DI work-9.479 km laid Pack-3 Agreement executed Chittur Project Dn - AE 3
17 May 2022 Part-1 Work in progress | 60% Completed | 17/05/2022 TOTAL 100.457KM LAID 1.) 90 mm pvc -8 kg 26.669 km laid 2.) 90mm pvc-6 kg-54.341 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.555 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80mm GI-0.850km Rider main 90mm 6 kg-1.799 km laid ,13)100 mm GI-0.156km , 14) 150mm GI-0.018km Part-2 Not Started | 17/05/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-1 Work in progress | 56% Completed | 17/05/2022 OHSR-Sidewall second lift concrete work complete and balance work in progress,350mm DI work-9.479 km laid Pack-3 Agreement executed Chittur Project Dn - AE 3
11 May 2022 Pack-1 Work in progress | 56% Completed | 11/05/2022 OHSR-Sidewall second lift concrete work complete and balance work in progress,350mm DI work-9.479 km laid Part-1 Work in progress | 60% Completed | 11/05/2022 TOTAL 99.307KM LAID 1.) 90 mm pvc -8 kg 26.569 km laid 2.) 90mm pvc-6 kg-54.311 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.555 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80mm GI-0.720km Rider main 90mm 6 kg-1.799 km laid ,13)100 mm GI-0.156km , 14) 150mm GI-0.018km Part-2 Not Started | 11/05/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-3 Not Started | 11/05/2022 Agreement executed Chittur Project Dn - AE 3
02 May 2022 Pack-1 Work in progress | 56% Completed | 02/05/2022 OHSR-Sidewall second lift concrete work in progress,350mm DI work-9.479 km laid Pack-3 Not Started | 02/05/2022 Agreement executed Pack-2-Part-1 Work in progress | 59% Completed | 02/05/2022 TOTAL 98.520KM LAID 1.) 90 mm pvc -8 kg 26.431 km laid 2.) 90mm pvc-6 kg-53.85 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.349 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.525 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80mm GI-0.570km Rider main 90mm 6 kg-1.799 km laid ,13)100 mm GI-0.149km , 14) 150mm GI-0.018km Pack-2-part-2 Not Started | 02/05/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has Chittur Project Dn - AE 3
18 Apr 2022 pack-1 Work in progress | 54% Completed | 18/04/2022 OHSR-Sidewall second lift shuttering and rft work in progress,350mm DI work-5.70km laid Part-1 Work in progress | 57% Completed | 18/04/2022 TOTAL 94.344KM LAID 1.) 90 mm pvc -8 kg 25.313 km laid 2.) 90mm pvc-6 kg-50.362 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.068 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, 12) 80mm GI-175.651m Rider main 90mm 6 kg-1.799 km laid ,13)100 mm GI-117M,14) 150mm GI-18 Part-2 Not Started | 18/04/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-3 Not Started | 18/04/2022 Agreement executed Chittur Project Dn - AE 3
06 Apr 2022 PACK-1 Work in progress | 54% Completed | 06/04/2022 OHSR-Sidewall first lift shuttering and rft work in progress,350mm DI work-5.70km laid PART-1 Work in progress | 56% Completed | 06/04/2022 TOTAL 94.344KM LAID 1.) 90 mm pvc -8 kg 25.313 km laid 2.) 90mm pvc-6 kg-50.362 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.068 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, 12) 80mm GI-175.651m Rider main 90mm 6 kg-1.799 km laid ,13)100 mm GI-117M,14) 150mm GI-18 PART-2 Not Started | 06/04/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD PACK-3 Not Started | 06/04/2022 Agreement executed Chittur Project Dn - AE 3