Overall Project Status

Status Date Overall Project Status Project Officer Contact
28 Oct 2022 Pack-1 Work in progress | 72% Completed | 28/10/2022 Plastering work in progress and , 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479m laid, Part-1 Work in progress | 66% Completed | 28/10/2022 1) GI pipe/pvc pipe linking works are in progress. and TOTAL 101.53KM LAID 1.) 90 mm pvc -8 kg 26.829 km laid 2.) 90mm pvc-6 kg-54.635KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.362Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.396 km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.186km Part-2 Not Started | 28/10/2022 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Pack-3 Work in progress | 28% Completed | 28/10/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-29.169 km 1.) 90 mm 6 kg-22890m supplied-6538.50m laid 2)90 mm 8 kg-15366m supplied and 10861 m laid 3) 110mm 6 kg-4278m supplied and 2332m laid 4)110mm 8kg-3150m supplied and 2480.80 m laid 5)140mm 6kg-3540 m supplied 1832.50 m laid 6)140mm 8 kg-384 m laid 7)160 mm 6 kg 2490 m supplied 1802 m laid 8) 160 mm 8 kg-1050 m supplied 906m 9)80 mm GI-219m laid 9)100 mm GI-66 M laid Chittur Project Dn - AE 3
21 Oct 2022 Pack-1 Work in progress | 72% Completed | 21/10/2022 plastering work in progress and , 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, part-1 Work in progress | 66% Completed | 21/10/2022 1) GI pipe/pvc pipe linking works are in progress. and TOTAL 101.44KM LAID 1.) 90 mm pvc -8 kg 26.829 km laid 2.) 90mm pvc-6 kg-54.632KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.356Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.396 km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.186km Pack-3 Work in progress | 26% Completed | 21/10/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-25.418 km 1.) 90 mm 6 kg-22890m supplied-6256.50m laid 2)90 mm 8 kg-15366m supplied and 7869 m laid 3) 110mm 6 kg-4278m supplied and 2332m laid 4)110mm 8kg-3150m supplied and 2294.80 m laid 5)140mm 6kg-3540 m supplied 1832.50 m laid 6)140mm 8 kg-246 m laid 7)160 mm 6 kg 2490 m supplied 1802 m laid 8) 160 mm 8 kg-1050 m supplied 906m 9)80 mm GI-66m laid 9)100 mm GI-66 M laid PART-2 Not Started | 21/10/2022 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Chittur Project Dn - AE 3
14 Oct 2022 Part-1 Work in progress | 66% Completed | 14/10/2022 1) GI pipe/pvc pipe linking works are in progress. and TOTAL 101.374KM LAID 1.) 90 mm pvc -8 kg 26.829 km laid 2.) 90mm pvc-6 kg-54.566KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.356Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.396 km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.186km Part-2 Not Started | 14/10/2022 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD) Pack-3 Work in progress | 23% Completed | 14/10/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-22.627 km 1.) 90 mm 6 kg-22890m supplied-5374.50m laid 2)90 mm 8 kg-15366m supplied and 7095 m laid 3) 110mm 6 kg-4278m supplied and 2332m laid 4)110mm 8kg-3150m supplied and 2294.80 m laid 5)140mm 6kg-3540 m supplied 1598.50 m laid 6)140mm 8 kg-246 m laid 7)160 mm 6 kg 2490 m supplied 1622 m laid 8) 160 mm 8 kg-1050 m supplied 198m 9)80 mm GI-66m laid 9)100 mm GI-53M laid Pack-1 Work in progress | 72% Completed | 14/10/2022 plastering work in progress and , 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, Chittur Project Dn - AE 3
08 Oct 2022 Pack-1 Work in progress | 71% Completed | 08/10/2022 OHSR-Cover slab concrete work completed ,curing work ,plastering work also progress and , 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, Part-1 Work in progress | 66% Completed | 08/10/2022 1) GI pipe/pvc pipe linking works are in progress. and TOTAL 101.146KM LAID 1.) 90 mm pvc -8 kg 26.829 km laid 2.) 90mm pvc-6 kg-54.456KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.356Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.332 km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.132km Part-2 Not Started | 08/10/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-3 Work in progress | 22% Completed | 08/10/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-20.931 km 1.) 90 mm 6 kg-22890m supplied-4792.50 m laid 2)90 mm 8 kg-15366m supplied and 7095 m laid 3) 110mm 6 kg-4278m supplied and 2307 m laid 4)110mm 8kg-3150m supplied and 2294.80 m laid 5)140mm 6kg-3540 m supplied 1597.50 m laid 6)140mm 8 kg-246 m laid 7)160 mm 6 kg 2490 m supplied 810 m laid 8) 160 mm 8 kg-1050 m supplied 9)80 mm GI-21m laid 9)100 mm GI-20M laid Chittur Project Dn - AE 3
30 Sep 2022 Phase-II-Pack-I Work in progress | 70% Completed | 26/09/2022 plastering work in progress and OHSR-Cover slab shuttering and reinforcement work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, PACK-2-part-1 Work in progress | 66% Completed | 26/09/2022 1) GI pipe/pvc pipe linking works are in progress. and TOTAL 101.071KM LAID 1.) 90 mm pvc -8 kg 26.754 km laid 2.) 90mm pvc-6 kg-54.456KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.356Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.332 km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.132km Pack-III Work in progress | 20% Completed | 26/09/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-18.936km 1.) 90 mm 6 kg-22890m supplied-4773.50m laid 2)90 mm 8 kg-15366m supplied and 6345 m laid 3) 110mm 6 kg-4278m supplied and 1647m laid 4)110mm 8kg-3150m supplied and 2294.80 m laid 5)140mm 6kg-3540 m supplied 1597.50 m laid 6)140mm 8 kg-246 m laid 7)160 mm 6 kg 2490 m supplied 264 m laid 8) 160 mm 8 kg-1050 m supplied 9)80 mm GI-21m laid PACK-2 Not Started | 26/09/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Chittur Project Dn - AE 3
26 Sep 2022 Phase-II-Pack-I Work in progress | 70% Completed | 26/09/2022 plastering work in progress and OHSR-Cover slab shuttering and reinforcement work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, PACK-2-part-1 Work in progress | 66% Completed | 26/09/2022 1) GI pipe/pvc pipe linking works are in progress. and TOTAL 101.071KM LAID 1.) 90 mm pvc -8 kg 26.754 km laid 2.) 90mm pvc-6 kg-54.456KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.356Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.332 km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.132km Pack-III Work in progress | 20% Completed | 26/09/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-18.936km 1.) 90 mm 6 kg-22890m supplied-4773.50m laid 2)90 mm 8 kg-15366m supplied and 6345 m laid 3) 110mm 6 kg-4278m supplied and 1647m laid 4)110mm 8kg-3150m supplied and 2294.80 m laid 5)140mm 6kg-3540 m supplied 1597.50 m laid 6)140mm 8 kg-246 m laid 7)160 mm 6 kg 2490 m supplied 264 m laid 8) 160 mm 8 kg-1050 m supplied 9)80 mm GI-21m laid PACK-2 Not Started | 26/09/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Chittur Project Dn - AE 3
10 Sep 2022 PHASE-2-PACK-2-PART-1 Work in progress | 65% Completed | 10/09/2022 GI pipe/pvc pipe linking works are in progress. and TOTAL 100.988KM LAID 1.) 90 mm pvc -8 kg 26.695 km laid 2.) 90mm pvc-6 kg-54.445 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.332 km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.132km Pack-1 Work in progress | 68% Completed | 10/09/2022 OHSR-Cover slab shuttering work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, Work started on 07.07.2022. Pack-III Work in progress | 15% Completed | 10/09/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-52.764km Total laid-7.724km 1.) 90 mm 6 kg-22890m supplied-3501.50m laid 2)90 mm 8 kg-15366m supplied 3) 110mm 6 kg-4278m supplied and 1383m laid 4)110mm 8kg-3150m supplied and 2067 m laid 5)140mm 6kg-3540 m supplied 1135.50 m laid 6)160 mm 6 kg 2490 m supplied 7) 160 mm 8 kg-1050 m supplied PACK-II-Part-II Not Started | 10/09/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Chittur Project Dn - AE 3
02 Sep 2022 PHASE-2-PACK-2-PART-1 Work in progress | 65% Completed | 02/09/2022 GI pipe/pvc pipe linking works are in progress. and TOTAL 100.988KM LAID 1.) 90 mm pvc -8 kg 26.695 km laid 2.) 90mm pvc-6 kg-54.445 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.332 km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.132km Pack-1 Work in progress | 68% Completed | 02/09/2022 OHSR-Cover slab shuttering work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, Work started on 07.07.2022. Pack-III Work in progress | 15% Completed | 02/09/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-52.764km Total laid-7.724km 1.) 90 mm 6 kg-22890m supplied-3501.50m laid 2)90 mm 8 kg-15366m supplied 3) 110mm 6 kg-4278m supplied and 1383m laid 4)110mm 8kg-3150m supplied and 2067 m laid 5)140mm 6kg-3540 m supplied 1135.50 m laid 6)160 mm 6 kg 2490 m supplied 7) 160 mm 8 kg-1050 m supplied PACK-II-Part-II Not Started | 02/09/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Chittur Project Dn - AE 3
25 Aug 2022 Part-1 Work in progress | 64% Completed | 25/08/2022 GI pipe/pvc pipe linking works are in progress. and TOTAL 100.837KM LAID 1.) 90 mm pvc -8 kg 26.695 km laid 2.) 90mm pvc-6 kg-54.424 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.202 km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.132km Part-II Not Started | 25/08/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-I Work in progress | 67% Completed | 25/08/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, OHSR-Staircase 5th flight concrete work completed PACK-3 Work in progress | 12% Completed | 25/08/2022 Work started on 07.07.2022. DI pipes and pvc pipes various dia are supplied in site Total supply-52.764km Total laid-6.158km 1.) 90 mm 6 kg-22890m supplied-3351.50m laid 2)90 mm 8 kg-15366m supplied 3) 110mm 6 kg-4278m supplied and 1239m laid 4)110mm 8kg-3150m supplied and 795.00m laid 5)140mm 6kg-3540 m supplied 1135.50 m laid 6)160 mm 6 kg 2490 m supplied 7) 160 mm 8 kg-1050 m supplied Chittur Project Dn - AE 3
24 Aug 2022 Part-1 Work in progress | 64% Completed | 24/08/2022 GI pipe/pvc pipe linking works are in progress. and TOTAL 100.837KM LAID 1.) 90 mm pvc -8 kg 26.695 km laid 2.) 90mm pvc-6 kg-54.424 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.350 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.202 km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.132km Part-II Not Started | 24/08/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD Pack-I Work in progress | 67% Completed | 24/08/2022 OHSR-Sidewall 3 rd lift concrete work complete and balance work in progress, 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479, OHSR-Staircase 5th flight concrete work completed PACK-3 Work in progress | 12% Completed | 24/08/2022 Work started on 07.07.2022. DI pipes and pvc pipes various dia are supplied in site Total supply-52.764km Total laid-6.158km 1.) 90 mm 6 kg-22890m supplied-3351.50m laid 2)90 mm 8 kg-15366m supplied 3) 110mm 6 kg-4278m supplied and 1239m laid 4)110mm 8kg-3150m supplied and 795.00m laid 5)140mm 6kg-3540 m supplied 1135.50 m laid 6)160 mm 6 kg 2490 m supplied 7) 160 mm 8 kg-1050 m supplied Chittur Project Dn - AE 3