Status Date |
Overall Project Status |
Project Officer |
Contact |
31 Mar 2022 |
PACK-2-PART-1
Work in progress | 56% Completed | 31/03/2022
TOTAL 94.344KM LAID 1.) 90 mm pvc -8 kg 25.313 km laid 2.) 90mm pvc-6 kg-50.362 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.068 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, 12) 80mm GI-175.651m Rider main 90mm 6 kg-1.799 km laid ,13)100 mm GI-117M,14) 150mm GI-18
PACK-1
Work in progress | 54% Completed
OHSR-Sidewall first lift shuttering and rft work in progress,350mm DI work-5.60km laid
PACK-3
Not Started | 31/03/2022
Agreement executed
PACK-2-PART2
HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD
|
Chittur Project Dn - AE 3 |
|
23 Mar 2022 |
Pack-1
Work in progress | 53% Completed | 23/03/2022
350mm DI k9 Pipe-1000 m supplied ,500m supplied laying work in progress
Part-1
Work in progress | 55% Completed | 23/03/2022
TOTAL 92.556KM LAID 1.) 90 mm pvc -8 kg 24.983 km laid 2.) 90mm pvc-6 kg-48.904 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.068 Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, 12) 80mm GI-175.651m Rider main 90mm 6 kg-1.799 km laid ,13)100 mm GI-117M,14) 150mm GI-18
Part-2
Not Started | 23/03/2022
HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD
Pack-3
Not Started | 23/03/2022
Agreement executed
|
Chittur Project Dn - AE 3 |
|
17 Mar 2022 |
Pack-1 Work in progress | 53% Completed | 17/03/2022 22LL karimkunnam OHSR-HAUNCH concrete work complete and sidewall first lift shuttering work and 350mm DI k9 Pipe-1000 m supplied ,laying work in progress
Part-1 Work in progress | 53% Completed | 17/03/2022 TOTAL 91 KM LAID
Part-2 Not Started | 17/03/2022 HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD
Pack-3 Not Started | 17/03/2022 Agreement executed
|
Chittur Project Dn - AE 3 |
|
16 Mar 2022 |
Pack-1
Work in progress | 53% Completed | 16/03/2022
22LL karimkunnam OHSR-HAUNCH concrete work complete and sidewall first lift shuttering work in progress
Part-1
Work in progress | 53% Completed | 16/03/2022
TOTAL 91 KM LAID 1.) 90 mm pvc -8 kg 24.371 km laid 2.) 90mm pvc-6 kg-48.202 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.068 Km laid 5.)140mm pvc-6kg-1.428Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, 12) 80mm GI-175.526m Rider main 90mm 6 kg-1.799 km laid ,13)100 mm GI-108M,14) 150mm GI-18
Part-2
Not Started | 16/03/2022
HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. EE is directed to prepare estimate for HDD
Pack-3
Not Started | 16/03/2022
Agreement executed
|
Chittur Project Dn - AE 3 |
|
15 Mar 2022 |
Pack-1
Work in progress | 52% Completed | 15/03/2022
22LL karimkunnam OHSR-HAUNCH concrete work complete and sidewall first lift shuttering work in progress
Part-1
Work in progress | 53% Completed | 15/03/2022
OTAL 88.622 KM LAID 1.) 90 mm pvc -8 kg 23.939km laid 2.) 90mm pvc-6 kg-46.40 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.068 Km laid 5.)140mm pvc-6kg-1.428Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, 12) 80mm GI-175.526m Rider main 90mm 6 kg-1.799 km laid
Part-2
Not Started | 15/03/2022
Waiting for approval of HDD work of Phase-II,the amount can be used for the work of HDD
Pack-3
Not Started | 15/03/2022
Agreement executed
|
Chittur Project Dn - AE 3 |
|
10 Mar 2022 |
Pack-1
Work in progress | 52% Completed | 10/03/2022
22LL karimkunnam OHSR-HAUNCH concrete work in progress
Part-1
Work in progress | 53% Completed | 10/03/2022
TOTAL 88.622 KM LAID 1.) 90 mm pvc -8 kg 23.939km laid 2.) 90mm pvc-6 kg-46.40 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.068 Km laid 5.)140mm pvc-6kg-1.428Km 6). 160mm pvc-6kg-1.761Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, 12) 80mm GI-175.526m Rider main 90mm 6 kg-1.799 km laid
Part-2
Not Started | 10/03/2022
Waiting for approval of HDD work of Phase-II,the amount can be used for the work of HDD
Pack-3
Not Started | 10/03/2022
Agreement executed
|
Chittur Project Dn - AE 3 |
|
03 Mar 2022 |
Pack-2-part-1
Work in progress | 52% Completed | 03/03/2022
TOTAL 86.575 KM LAID 1.) 90 mm pvc -8 kg 23.807 km laid 2.) 90mm pvc-6 kg-44.714 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-5.948 Km laid 5.)140mm pvc-6kg-1.428Km 6). 160mm pvc-6kg-1.733Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, 12) 80mm GI-94.526m Rider main 90mm 6 kg-1.799 km laid
Pack-2-part-2
Not Started | 03/03/2022
Waiting for approval of HDD work of Phase-II,the amount can be used for the work of HDD
Pack-1
Work in progress | 52% Completed | 03/03/2022
22LL karimkunnam OHSR-HAUNCH Shuttering work in progress
Pack-3
Not Started | 03/03/2022
Agreement executed
|
Chittur Project Dn - AE 3 |
|
22 Feb 2022 |
Pack-1
Work in progress | 52% Completed | 22/02/2022
22LL karimkunnam OHSR-HAUNCH Shuttering work in progress
Part-1
Work in progress | 50% Completed | 22/02/2022
TOTAL 84.959 KM LAID 1.) 90 mm pvc -8 kg 22.961 km laid 2.) 90mm pvc-6 kg-44.215 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-5.93 Km laid 5.)140mm pvc-6kg-1.416Km 6). 160mm pvc-6kg-1.518Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, 12) 80mm GI-94.50m Rider main 90mm 6 kg-1.799 km laid
Part-2
Not Started | 22/02/2022
Waiting for approval of HDD work of Phase-II,the amount can be used for the work of HDD
Pack-3
Not Started | 22/02/2022
Agreement executed
|
Chittur Project Dn - AE 3 |
|
14 Feb 2022 |
Pack-1
Work in progress | 52% Completed | 14/02/2022
22LL karimkunnam OHSR -inside column concreting 2nd lift.concrete work and sidewall reinforcement work in progress
Pack-2-part-2
Not Started | 14/02/2022
Waiting for approval of HDD work of Phase-II,the amount can be used for the work of HDD
Part-1
Work in progress | 48% Completed | 14/02/2022
TOTAL 83.287 KM LAID 1.) 90 mm pvc -8 kg 22.739 km laid 2.) 90mm pvc-6 kg-43.219 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-5.93 Km laid 5.)140mm pvc-6kg-1.416Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, Rider main 90mm 6 kg-1.799 km laid
Pack-3
Not Started | 14/02/2022
Agreement executed
|
Chittur Project Dn - AE 3 |
|
06 Feb 2022 |
Pack-1
Work in progress | 52% Completed | 06/02/2022
22LL karimkunnam OHSR -inside column concreting 2nd lift. work in progress
Part-1
Work in progress | 48% Completed | 06/02/2022
TOTAL 83.287 KM LAID 1.) 90 mm pvc -8 kg 22.739 km laid 2.) 90mm pvc-6 kg-43.219 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-5.93 Km laid 5.)140mm pvc-6kg-1.416Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, Rider main 90mm 6 kg-1.799 km laid
Part-2
Not Started | 06/02/2022
Waiting for approval of HDD work of Phase-II,the amount can be used for the work of HDD
Pack-3
Not Started | 06/02/2022
Agreement executed
|
Chittur Project Dn - AE 3 |
|