Status Date |
Overall Project Status |
Project Officer |
Contact |
02 Feb 2022 |
Phase-2-pack-2-part-2
Waiting for approval of HDD work of Phase-II,the amount can be used for the work of HDD |
Chittur Project Dn - AE 3 |
|
01 Feb 2022 |
Pack-1
Work in progress | 52% Completed | 01/02/2022
22LL karimkunnam OHSR -inside column concreting 2nd lift. work in progress
Part-2
Not Started | 01/02/2022
Revised estimate prepared and submitted for approval
Part-1
Work in progress | 48% Completed | 01/02/2022
TOTAL 81.153 KM LAID 1.) 90 mm pvc -8 kg 22.163 km laid 2.) 90mm pvc-6 kg-42.171 KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-5.42 Km laid 5.)140mm pvc-6kg-1.416Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, Rider main 90mm 6 kg-1.799 km laid Total 81.153km laid
Pack-3
Not Started | 01/02/2022
Agreement to be executed
|
Chittur Project Dn - AE 3 |
|
26 Jan 2022 |
Pack-1
Work in progress | 52% Completed | 26/01/2022
side wall first lift shuttering and reinforcement work and stair fourth flight concrete work in progress
part-1
Work in progress | 46% Completed | 26/01/2022
TOTAL 78.946 KM LAID 1.) 90 mm pvc -8 kg 22.079km laid 2.) 90mm pvc-6 kg-40.311 KM laid 3.) 110 mm pvc 8 kg- 2.243 k m laid 4.)110mm pvc -6kg-5.190 Km laid 5.)140mm pvc-6kg-1.416Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, Rider main 90mm 6 kg-1.799 km laid
Part-2
Not Started | 26/01/2022
Revised estimate prepared and submitted for approval
Pack-3
Revised work order issued wide order NO KWA/PHC/PKD/KIIFB-VANDAZHI-PACKAGE-III-dtd -31.12.2021
|
Chittur Project Dn - AE 3 |
|
20 Jan 2022 |
Pack-1
Work in progress | 53% Completed | 20/01/2022
side wall first lift shuttering and reinforcement work in progress
pack-2-part-1
Work in progress | 45% Completed | 20/01/2022
TOTAL 76.542 KM LAID 1.) 90 mm pvc -8 kg 21.707km laid 2.) 90mm pvc-6 kg-38.693 KM laid 3.) 110 mm pvc 8 kg- 2.243 k m laid 4.)110mm pvc -6kg-4.776 Km laid 5.)140mm pvc-6kg-1.416Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-1.489 Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, Rider main 90mm 6 kg-1.799 km laid Total 76.542km laid
Pack-2-Part-2
Not Started | 20/01/2022
Revised estimate prepared and submitted for approval
Pack-3
Not Started | 20/01/2022
Revised work order issued wide order NO KWA/PHC/PKD/KIIFB-VANDAZHI-PACKAGE-III-dtd -31.12.2021
|
Chittur Project Dn - AE 3 |
|
12 Jan 2022 |
PACK-I
Work in progress | 52% Completed | 12/01/2022
side wall first lift shuttering and reinforcement work in progress
PACK-2-PART-I
Work in progress | 40% Completed | 12/01/2022
TOTAL 75.045 KM LAID 1.) 90 mm pvc -8 kg 21.401km laid 2.) 90mm pvc-6 kg-37.967 KM laid 3.) 110 mm pvc 8 kg- 2.228 k m laid 4.)110mm pvc -6kg-4.626 Km laid 5.)140mm pvc-6kg-1.416Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-1.189 Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, Rider main 90mm 6 kg-1.799 km laid Total 75.045km laid
Pack-2-part-2
Not Started | 12/01/2022
Revised estimate prepared and submitted for approval
Pack-3
Not Started | 12/01/2022
Revised work order issued wide order NO KWA/PHC/PKD/KIIFB-VANDAZHI-PACKAGE-III-dtd -31.12.2021
|
Chittur Project Dn - AE 3 |
|
10 Jan 2022 |
Pack-1
Work in progress | 52% Completed | 10/01/2022
side wall first lift shuttering and reinforcement work in progress
part-1
Work in progress | 40% Completed | 10/01/2022
TOTAL 73.596 KM LAID 1.) 90 mm pvc -8 kg 21.359 km laid 2.) 90mm pvc-6 kg-37.136 KM laid 3.) 110 mm pvc 8 kg- 2.216k m laid 4.)110mm pvc -6kg-4.614Km laid 5.)140mm pvc-6kg-1.416Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-0.637Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, Rider main 90mm 6 kg-1.799 km laid Total 71.900km laid
Part-2
Not started | 0% Completed | 10/01/2022
Revised estimate prepared and submitted for approval Not Started | 10/01/2022
Pack-3
Revised work order issued wide order NO KWA/PHC/PKD/KIIFB-VANDAZHI-PACKAGE-III-dtd -31.12.2021
|
Chittur Project Dn - AE 3 |
|
03 Jan 2022 |
pack-3
Not Started | 02/01/2022
Revised work order issued wide order NO KWA/PHC/PKD/KIIFB-VANDAZHI-PACKAGE-III-dtd -31.12.2021
Pack-1
Work in progress | 52% Completed | 02/01/2022
side wall first lift shuttering and reinforcement work in progress
pack-2-part-1
Work in progress | 40% Completed | 02/01/2022
TOTAL 71.900 KM LAID 1.) 90 mm pvc -8 kg 20.386 km laid 2.) 90mm pvc-6 kg-36.479 KM laid 3.) 110 mm pvc 8 kg- 2.216k m laid 4.)110mm pvc -6kg-4.614Km laid 5.)140mm pvc-6kg-1.416Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, Rider main 90mm 6 kg-1.799 km laid Total 71.900km laid
Pack-2-part-2
Not Started | 02/01/2022
Revised estimate prepared and submitted for approval
|
Chittur Project Dn - AE 3 |
|
28 Dec 2021 |
Pack-1
Work in progress | 52% Completed | 28/12/2021
side wall first lift shuttering and reinforcement work in progress
pack-2-part-1
Work in progress | 40% Completed | 28/12/2021
TOTAL 71.900 KM LAID 1.) 90 mm pvc -8 kg 20.386 km laid 2.) 90mm pvc-6 kg-36.479 KM laid 3.) 110 mm pvc 8 kg- 2.216k m laid 4.)110mm pvc -6kg-4.614Km laid 5.)140mm pvc-6kg-1.416Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m, Rider main 90mm 6 kg-1.799 km laid Total 71.900km laid
Pack-3
Not Started | 28/12/2021
Revised estimate prepared and submitted for approved
Pack-2-part-2
Not Started | 22/12/2021
Revised estimate prepared and submitted for approval
|
Chittur Project Dn - AE 3 |
|
22 Dec 2021 |
Part-1
Work in progress | 37% Completed | 22/12/2021
TOTAL 70.4377KM LAID 1.) 90 mm pvc -8 kg 20.08km laid 2.) 90mm pvc-6 kg-35.532KM laid 3.) 110 mm pvc 8 kg- 2.006k m laid 4.)110mm pvc -6kg-4.614Km laid 5.)140mm pvc-6kg-1.416Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-48m,Rider main 90mm 6 kg-1.799 km laid Total 70.4377km laid
Pack-1
Work in progress | 52% Completed | 22/12/2021
side wall first lift shuttering and reinforcement work in progress
pack-3
Not Started | 22/12/2021
Revised estimate prepared and submitted for approval
Part-2
Not Started | 22/12/2021
Revised estimate prepared and submitted for approval
|
Chittur Project Dn - AE 3 |
|
19 Dec 2021 |
Pack-1
Work in progress | 51% Completed | 19/12/2021
side wall first lift shuttering and reinforcement work in progress
pack-2-part-1
Work in progress | 36% Completed | 19/12/2021
TOTAL 68.073 KM LAID 1.) 90 mm pvc -8 kg 19.60 m laid 2.) 90mm pvc-6 kg-33.959KM laid 3.) 110 mm pvc 8 kg- 1.908 m laid 4.)110mm pvc -6kg-4.614Km laid 5.)140mm pvc-6kg-1.314Km 6). 160mm pvc-6kg-1.158Km laid 7).160mm pvc -8kg-0.571Km laid 8).300 MM di k9-0.5465Km laid 9). 200mm DI K9-1.119KM laid 10).250mm DI pipe-0.5314Km Rider main 90mm 6 kg-1.78 m laid Total 68.073km laid
Pack-2-part-2
Not Started | 19/12/2021
Revised estimate prepared and submitted for approval
Pack-3
Not Started | 19/12/2021
Revised estimate prepared and submitted for approval
|
Chittur Project Dn - AE 3 |
|