Overall Project Status

Status Date Overall Project Status Project Officer Contact
20 Jan 2023 Part-1 Work in progress | 67% Completed | 20/01/2023 GI pipe/pvc pipe linking works are in progress. and TOTAL 110.637 KM LAID 1.) 90 mm pvc -8 kg 27.039 km laid 2.) 90mm pvc-6 kg-54.718KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.364Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M Part-2 Not Started | 20/01/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Pack-1 Work in progress | 81% Completed | 20/01/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 14.0131 km laid, Pack- Work in progress | 43% Completed | 20/01/2023 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-53.398 km 1.) 90 mm 6 kg-22890m supplied- 18834.50 m laid 2) 90 mm 8 kg-15600m supplied and 18087.00 m laid 3) 110mm 6 kg-4278m supplied and 2965 m laid 4) 110mm 8kg-3150m supplied and 3537.80 m laid 5) 140mm 6kg-3540 m supplied 2561.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2825 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI- 696.7 m laid 10)100 mm GI-148.50 M laid 11)125mm GI-33M 12)150MM GI-30M Chittur Project Dn - AE 3
06 Jan 2023 Part-1 Work in progress | 67% Completed | 06/01/2023 GI pipe/pvc pipe linking works are in progress. and TOTAL 110.637 KM LAID 1.) 90 mm pvc -8 kg 27.039 km laid 2.) 90mm pvc-6 kg-54.718KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.364Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M Package-1 Work in progress | 79% Completed | 06/01/2023 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 13.4781km laid, Part-2 Not Started | 06/01/2023 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Pack-3 Work in progress | 40% Completed | 06/01/2023 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-49.298 km 1.) 90 mm 6 kg-22890m supplied- 17028.50 m laid 2) 90 mm 8 kg-15600m supplied and 16552.00 m laid 3) 110mm 6 kg-4278m supplied and 2701 m laid 4) 110mm 8kg-3150m supplied and 3152.80 m laid 5) 140mm 6kg-3540 m supplied 2477.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2807 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9) 80 mm GI-630.70 m laid 10)100 mm GI-136.50 M laid 11)125mm GI-33M 12)150MM GI-30M Chittur Project Dn - AE 3
30 Dec 2022 PACK-III-PART-1 Work in progress | 67% Completed | 30/12/2022 GI pipe/pvc pipe linking works are in progress. and TOTAL 110.637 KM LAID 1.) 90 mm pvc -8 kg 27.039 km laid 2.) 90mm pvc-6 kg-54.718KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.364Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9853km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M PACK-3 Work in progress | 38% Completed | 30/12/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-48.053 km 1.) 90 mm 6 kg-22890m supplied- 16596.50 m laid 2) 90 mm 8 kg-15366m supplied and 16186.00 m laid 3) 110mm 6 kg-4278m supplied and 2701 m laid 4) 110mm 8kg-3150m supplied and 2804.80 m laid 5) 140mm 6kg-3540 m supplied 2477.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2807 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9)80 mm GI-539.70 m laid 10)100 mm GI-128.50 M laid 11)125mm GI-33M 12)150MM GI-30M PACK-1 Work in progress | 78% Completed | 30/12/2022 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 13.0985km laid, PACK-2-PART-2 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized Chittur Project Dn - AE 3
22 Dec 2022 Pack-1 Work in progress | 76% Completed | 22/12/2022 OHSR plastering work and compound wall work are also in progress and, 350mm DI work- 14569.50M PIPE supplied at site and 12.105km laid, PART-1 Work in progress | 67% Completed | 22/12/2022 GI pipe/pvc pipe linking works are in progress. and TOTAL 110.431 KM LAID 1.) 90 mm pvc -8 kg 26.907 km laid 2.) 90mm pvc-6 kg-54.692KM laid 3.) 110 mm pvc 8 kg- 2.277 k m laid 4.)110mm pvc -6kg-6.364Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.9805 km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.847km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m 16)125mm GI-30M PART-2 Not Started | 22/12/2022 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. PACK-3 Work in progress | 38% Completed | 22/12/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-46.082 km 1.) 90 mm 6 kg-22890m supplied- 15086.50 m laid 2) 90 mm 8 kg-15366m supplied and 16150.00 m laid 3) 110mm 6 kg-4278m supplied and 2699m laid 4) 110mm 8kg-3150m supplied and 2492.80 m laid 5) 140mm 6kg-3540 m supplied 2439.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2792 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9)80 mm GI-498.70 m laid 10)100 mm GI-121.50 M laid 11)125mm GI-23M 12)150MM GI-30M Chittur Project Dn - AE 3
10 Dec 2022 PART-2 Not Started | 10/12/2022 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. PACK-1 Work in progress | 75% Completed | 10/12/2022 OHSR plastering work and compound wall work are also in progress and , 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 10.5295km laid, Pack-3 Work in progress | 35% Completed | 10/12/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-43.185 km 1.) 90 mm 6 kg-22890m supplied- 14690.50 m laid 2) 90 mm 8 kg-15366m supplied and 13977.00 m laid 3) 110mm 6 kg-4278m supplied and 2698m laid 4) 110mm 8kg-3150m supplied and 2492.80 m laid 5) 140mm 6kg-3540 m supplied 2438.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2576 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9)80 mm GI-403.70 m laid 10)100 mm GI-113.50 M laid 11)125mm GI-16M 12)150MM GI-30M Part-1 Work in progress | 67% Completed | 10/12/2022 GI pipe/pvc pipe linking works are in progress. and TOTAL 110.208 KM LAID 1.) 90 mm pvc -8 kg 26.906 km laid 2.) 90mm pvc-6 kg-54.674KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.362Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.8405km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m Chittur Project Dn - AE 3
02 Dec 2022 Pack-1 Work in progress | 73% Completed | 02/12/2022 plastering work and compound wall work are also in progress and , 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 10.271km laid, pack-3 Work in progress | 35% Completed | 02/12/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-42.588 km 1.) 90 mm 6 kg-22890m supplied- 14677.50 m laid 2) 90 mm 8 kg-15366m supplied and 13977.00 m laid 3) 110mm 6 kg-4278m supplied and 2332m laid 4) 110mm 8kg-3150m supplied and 2492.80 m laid 5) 140mm 6kg-3540 m supplied 2438.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2420 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9)80 mm GI-341.20 m laid 10)100 mm GI-113.50 M laid 11)125mm GI-16M 12)150MM GI-30M Part-1 Work in progress | 67% Completed | 02/12/2022 GI pipe/pvc pipe linking works are in progress. and TOTAL 110.052 KM LAID 1.) 90 mm pvc -8 kg 26.840 km laid 2.) 90mm pvc-6 kg-54.642KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.362Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.782km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m Part-2 Not Started | 02/12/2022 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Chittur Project Dn - AE 3
24 Nov 2022 Pack-1 Work in progress | 73% Completed | 24/11/2022 plastering work and compound wall work are also in progress and , 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 10.271km laid, PACK-3 Work in progress | 34% Completed | 24/11/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-41.120 km 1.) 90 mm 6 kg-22890m supplied- 14050.50 m laid 2) 90 mm 8 kg-15366m supplied and 13419 m laid 3) 110mm 6 kg-4278m supplied and 2332m laid 4) 110mm 8kg-3150m supplied and 2492.80 m laid 5) 140mm 6kg-3540 m supplied 2168.50 m laid 6) 140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2420 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9)80 mm GI-327.70 m laid 10)100 mm GI-113.50 M laid 11)125mm GI-16M 12)150MM GI-30M Pack-2-part-1 Work in progress | 67% Completed | 24/11/2022 GI pipe/pvc pipe linking works are in progress. and TOTAL 110.036KM LAID 1.) 90 mm pvc -8 kg 26.830 km laid 2.) 90mm pvc-6 kg-54.642KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.362Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.627km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.186km 15)200 mm MS pipe-9.40m Part-2 Not Started | 24/11/2022 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized Chittur Project Dn - AE 3
22 Nov 2022 PACK-1 Work in progress | 72% Completed | 22/11/2022 plastering work and compound wall work are also in progress and , 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479m laid, PHASE-II-PACK-2-PART-1 Work in progress | 67% Completed | 22/11/2022 GI pipe/pvc pipe linking works are in progress. and TOTAL 110.00KM LAID 1.) 90 mm pvc -8 kg 26.830 km laid 2.) 90mm pvc-6 kg-54.641KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.362Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.602km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.186km PACK-3 Work in progress | 30% Completed | 22/11/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-37.00 km 1.) 90 mm 6 kg-22890m supplied-10996.50m laid 2)90 mm 8 kg-15366m supplied and 12411 m laid 3) 110mm 6 kg-4278m supplied and 2332m laid 4)110mm 8kg-3150m supplied and 2492.80 m laid 5)140mm 6kg-3540 m supplied 2168.50 m laid 6)140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2420 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9)80 mm GI-305.20m laid 10)100 mm GI-113.50 M laid 11)125mm GI-16M 12)150MM GI-30M PACK-2 Not Started | 22/11/2022 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Chittur Project Dn - AE 3
10 Nov 2022 Pack-1 Work in progress | 72% Completed | 10/11/2022 plastering work and compound wall work are also in progress and , 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479m laid, part-1 Work in progress | 66% Completed | 10/11/2022 1) GI pipe/pvc pipe linking works are in progress. and TOTAL 101.621KM LAID 1.) 90 mm pvc -8 kg 26.829 km laid 2.) 90mm pvc-6 kg-54.638KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.362Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.506km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.186km Pack-3 Work in progress | 29% Completed | 10/11/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-32.998 km 1.) 90 mm 6 kg-22890m supplied-8884.50m laid 2)90 mm 8 kg-15366m supplied and 11391.00 m laid 3) 110mm 6 kg-4278m supplied and 2332m laid 4)110mm 8kg-3150m supplied and 2492.80 m laid 5)140mm 6kg-3540 m supplied 2168.50 m laid 6)140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 2420 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9)80 mm GI-305.20m laid 10)100 mm GI-113.50 M laid 11)125mm GI-16M 12)150MM GI-30M Part-2 Not Started | 10/11/2022 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Chittur Project Dn - AE 3
04 Nov 2022 Paet-2 Not Started | 04/11/2022 Revised drawing submitted on 06.10.2022 as per the direction from NHAI,Palakkad,awaiting for approval -(HDD along NH at Wadakkanchery area. NHAI will not permit excavation along the service road and is insisting HDD for nearly 7km. There are many branches on either side and so pipes will have to be laid on both sides. Acquisition of land on either side is an option, but the NHAI has plans for widening plans on the anvil, which is not finalized. Pack-3 Work in progress | 29% Completed | 03/11/2022 DI pipes and pvc pipes various dia are supplied in site Total supply-122km Total laid-30.00 km 1.) 90 mm 6 kg-22890m supplied-7042.50m laid 2)90 mm 8 kg-15366m supplied and 11229.00 m laid 3) 110mm 6 kg-4278m supplied and 2332m laid 4)110mm 8kg-3150m supplied and 2492.80 m laid 5)140mm 6kg-3540 m supplied 1832.50 m laid 6)140mm 8 kg-648 m laid 7)160 mm 6 kg 2490 m supplied 1802 m laid 8) 160 mm 8 kg-1050 m supplied 996m 9)80 mm GI-286.70m laid 10)100 mm GI-91.50 M laid 11)125mm GI-16M 12)150MM GI-30M Part-1 Work in progress | 66% Completed | 04/11/2022 1) GI pipe/pvc pipe linking works are in progress. and TOTAL 101.586KM LAID 1.) 90 mm pvc -8 kg 26.829 km laid 2.) 90mm pvc-6 kg-54.635KM laid 3.) 110 mm pvc 8 kg- 2.276 k m laid 4.)110mm pvc -6kg-6.362Km laid 5.)140mm pvc-6kg-1.530Km 6). 160mm pvc-6kg-1.843Km laid 7).160mm pvc -8kg-1.558 Km laid 8).300 MM DI k9-0.5465Km laid 9). 200mm DI K9-1.195 KM laid 10).250mm DI pipe-0.5501Km 11)140mm pvc 8 kg-0.048km, 12) 80 mm GI- 1.452km Rider main 90mm 6 kg-1.803 km laid , 13)100 mm GI-1.819km , 14) 150mm GI-0.186km Pack-1 Work in progress | 72% Completed | 04/11/2022 plastering work in progress and , 350mm DI work- 14569.50M PIPE SUPPLIED AT SITE 9.479m laid, Chittur Project Dn - AE 3