| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 09 Jun 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed. Very slow progress. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed.Roof slab Re- inforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 75363.20m. Parachantha OHSR - Plinth beam shuttering work progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 06 Jun 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed. Very slow progress. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed.Roof slab Re- inforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 75363.20m. Parachantha OHSR - Plinth beam shuttering work progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AE 4 | |
| 04 Jun 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed. Very slow progress. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed.Roof slab Re- inforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing.Total laid qty 75363.20m. Parachantha OHSR - Plinth beam steel work progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 31 May 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed. Very slow progress. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall first lift concreting completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing.Total laid qty 75363.20m. Parachantha OHSR - column concreting progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 28 May 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed. Very slow progress. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall first lift concreting completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing.Total laid qty 75363.20m. Parachantha OHSR - column concreting progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 23 May 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed. Very slow progress. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall first lift concreting completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing.Total laid qty 75363.20m. Parachantha OHSR - column concreting progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 17 May 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed. Very slow progress. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall first lift concreting completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing.Total laid qty 75363.20m. Parachantha OHSR - column concreting progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 12 May 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall first lift concreting completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing.Total laid qty 74445.92m. Parachantha OHSR - column concreting progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 07 May 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall first lift concreting completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing.Total laid qty 60891m. Parachantha OHSR - column concreting progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 28 Apr 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Steel work of side wall progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - column work progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 |