Overall Project Status

Status Date Overall Project Status Project Officer Contact
24 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for OHSR foundation completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR PCC for foundation completed. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
23 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for OHSR foundation completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR PCC for foundation completed. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
22 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
21 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
20 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,450,500mm DI and 90,110,160mm uPVC pipe laying progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
18 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,450,500mm DI and 90,110,160mm uPVC pipe laying progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
17 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,450,500mm DI and 90,110,160mm uPVC pipe laying progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
16 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
15 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
14 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1