| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for OHSR foundation completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR PCC for foundation completed. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 23 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for OHSR foundation completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR PCC for foundation completed. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 22 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 21 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 20 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,450,500mm DI and 90,110,160mm uPVC pipe laying progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 18 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,450,500mm DI and 90,110,160mm uPVC pipe laying progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 17 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,450,500mm DI and 90,110,160mm uPVC pipe laying progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 16 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 15 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 14 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 |