Projects

  
Search ongoing projects Example: ‘project code’ or ’project name’ or ’location’

Overall Project Status

Status Date Overall Project Status Project Officer Contact
25 Jul 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 81247.20m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
15 Jul 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 81247.20m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
08 Jul 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 81247.20m. Parachantha OHSR - column concreting progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
03 Jul 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 81247.20m. Parachantha OHSR - column concreting progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
01 Jul 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, progressing. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 79659.92m. Parachantha OHSR - Plinth beam concreting completed . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
27 Jun 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, progressing. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 79659.92m. Parachantha OHSR - Plinth beam concreting completed . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
25 Jun 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, progressing. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 79659.92m. Parachantha OHSR - Plinth beam concreting completed . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
21 Jun 2025 Package 1- 99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, progressing. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 79659.92m. Parachantha OHSR - Plinth beam concreting completed . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
19 Jun 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed,progressing. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Re- inforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 79659.920m. Parachantha OHSR - Plinth beam concreting completed . Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
12 Jun 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed. Very slow progress. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Re- inforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 75363.20m. Parachantha OHSR - Plinth beam concreting completed . Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1