| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 25 Jul 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 81247.20m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 15 Jul 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 81247.20m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 08 Jul 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 81247.20m. Parachantha OHSR - column concreting progressing . Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 03 Jul 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 81247.20m. Parachantha OHSR - column concreting progressing . Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 01 Jul 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, progressing. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 79659.92m. Parachantha OHSR - Plinth beam concreting completed . Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 27 Jun 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, progressing. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 79659.92m. Parachantha OHSR - Plinth beam concreting completed . Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 25 Jun 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, progressing. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 79659.92m. Parachantha OHSR - Plinth beam concreting completed . Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 21 Jun 2025 | Package 1- 99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, progressing. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 79659.92m. Parachantha OHSR - Plinth beam concreting completed . Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 19 Jun 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed,progressing. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Re- inforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 79659.920m. Parachantha OHSR - Plinth beam concreting completed . Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 12 Jun 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed. Very slow progress. Package 3- Ongoing 15% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Side wall concreting completed. Roof slab Re- inforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 75363.20m. Parachantha OHSR - Plinth beam concreting completed . Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 |