| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Nov 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 31 Oct 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 27 Oct 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 23 Oct 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 15 Oct 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 07 Oct 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-40% completed, Malayil OHSR work progressing. Package 3- Ongoing 45% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 85107.64m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 03 Oct 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 85107.64m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 23 Sep 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 85107.64m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. | Alappuzha KIIFB - EE | |
| 19 Sep 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 85107.64m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 16 Sep 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 85107.64m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 |