Status Date Overall Project Status Project Officer Contact
05 Jun 2023 As per the minutes of the meeting held on 03-05-2023 at KIIFB Main Conference Hall, KWA was directed to seek Government AS by revising the schedule in two phases. KIIFB would take up the 1st phase now. ie. 50% of new proposal = 50% of Rs.434.443Cr. = Rs.217.221Cr. as Phase 1 . The DPR for Phase 1 for the subject work amounting to ₹217.221 crores is submitted for revised Administrative Sanction. Packages 1, 2, 3, 5 and additional works of new well and municipality road restoration are included in the Phase 1 of the DER. Package I- Construction of 35 MLD WTP completed. The trial running and commissioning will de done after getting power connection . For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam concrete work completed on 1/06/2023. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13143m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid . Package III- Work tendered, 3 times extended, no bidders received. Package V - works completed. The package IV work amounting to Rs 206 crore which is included in 2 nd phase is placed in the JJM reappropriation Kottayam Project Dn AEE2 KIFFB
25 May 2023 Package I- Construction of 35 MLD WTP completed. The trial running and commissioning will de done after getting power connection . For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13143m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid . Package III- Work tendered, 3 times extended, no bidders received. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - works completed. Kottayam Project Dn AEE2 KIFFB
11 Apr 2023 Package I- Construction of 35 MLD WTP completed. The trial running and commissioning will de done after getting power connection . For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13143m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid . Package III- Work retendered and the due date extended up to 19.04.2023. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - works completed. Alappuzha KIIFB - AE 1
11 Apr 2023 Package I- Construction of 35 MLD WTP completed. The trial running and commissioning will be done after getting power connection. For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13143m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid . Package III- Work tendered. The due date extended to 20.03.2023. Technical Bid opening on 21.03.2023.. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - Pipe laying- 110mm PVC pipe 5397m laid, 90mm PVC pipe 7525m, and 160mm PVC 2068m ,200mm DI 989m, 250mm DI 580m laid Alappuzha KIIFB - AE 1
18 Mar 2023 Package I- Construction of 35 MLD WTP completed. Erection of 270 Hp raw water pump sets completed. For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13143m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid . Package III- Work tendered. The due date extended to 20.03.2023. Technical Bid opening on 21.03.2023.. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - Pipe laying- 110mm PVC pipe 5397m laid, 90mm PVC pipe 7525m, and 160mm PVC 2068m ,200mm DI 989m, 250mm DI 580m laid Alappuzha KIIFB - AE 1
18 Mar 2023 Package I- Construction of 35 MLD WTP completed. Erection of 270 Hp raw water pump sets completed. For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13137m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 438m laid. 200 mm DI Pipe 446 m laid . Package III- Work tendered. The due date extended to 20.03.2023. Technical Bid opening on 21.03.2023.. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - Pipe laying- 110mm PVC pipe 5397m laid, 90mm PVC pipe 7501m, and 160mm PVC 2060m ,200mm DI 989m, 250mm DI 580m laid Alappuzha KIIFB - AE 1
17 Mar 2023 Package I- Construction of 35 MLD WTP completed. Erection of 270 Hp raw water pump sets completed. For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13137m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 438m laid. 200 mm DI Pipe 446 m laid . Package III- Work tendered. The due date extended to 20.03.2023. Technical Bid opening on 21.03.2023.. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - Pipe laying- 110mm PVC pipe 5397m laid, 90mm PVC pipe 7501m, and 160mm PVC 2060m ,200mm DI 989m, 250mm DI 580m laid Alappuzha KIIFB - AE 1
13 Mar 2023 Package I- Construction of 35 MLD WTP completed. Erection of 270 Hp raw water pump sets completed. For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13137m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 438m laid. 200 mm DI Pipe 446 m laid . Package III- Work tendered. The due date extended to 20.03.2023. Technical Bid opening on 21.03.2023.. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - Pipe laying- 110mm PVC pipe 5397m laid, 90mm PVC pipe 7129m, and 160mm PVC 1930m ,200mm DI 705m, 250mm DI 580m laid Alappuzha KIIFB - AE 1
21 Jan 2023 Package I- Construction of 35 MLD WTP completed. Erection of 270 Hp raw water pump sets in progress. For electrical connection to RWPH and WTP fund requested to KIIFB for depositing in KSEB. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13101m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 438m laid. 200 mm DI Pipe 446 m laid . Package III- Tender work is in progress. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - Pipe laying- 110mm PVC pipe 3624m laid, 90mm PVC pipe 5292m, and 160mm PVC 1110m laid. Alappuzha KIIFB - AE 1
10 Jul 2022 Package 1 - 35MLD WTP-Plate settler clarifier -Civil works completed. Mechanical work–Erection of SS plate for Plate settler completed. Erection of paddle wheel and motor drive in Flocculator and scrapper and motor drive in clarifier completed. Clearwater sump, pump house, filter house, chemical house, chlorine room- civil works completed. Filter house- Filter house pipe gallery DI pipe, fitting, valve erection completed clear water channel work completed. WWT- RCC work completed. OHSR civil work completed. Raw water pumping main- 700mm DI K9 pipe laying-2400m completed. 110/90/75mm PVC pipe distribution network laying work-2000m completed. Civil works of 750kVA/63kVA transformer room at Intake well site Pampa river basin RCC work completed. Retaining wall at RWPH site completed. 400kVA Transformer room at WTP site civil works completed. Aerator - works completed. Transformer 750/400/63kVA supplied at site. Raw water pumps and clear water pumps were supplied at the site and erection of clear water pumps completed. Construction of settling tank started. Package 2 - Concreting of raft foundation for OHSR is planned to be executed on 12/7/2022. Pipe laying- 110mm PVC pipe 9679m laid, 160mm PVC pipeline 12243m, and 90mm PVC pipe 6852m laid. 250 mm DI Pipe 288m laid. 200 mm DI Pipe 96 m laid (Total laid length=29158m). Package 3 - As per new directions, the detailed design of OHSRs is given to College of Engineering, Trivandrum for scrutiny. Road restoration estimates as per latest GO has been prepared. Package 4 - As per new directions, the detailed design of OHSRs is given to College of Engineering, Trivandrum for scrutiny. Road restoration estimates as per latest GO is under preparation. Alappuzha KIIFB - AE 1