Overall Project Status

Status Date Overall Project Status Project Officer Contact
09 Sep 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 85107.64m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
01 Sep 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 85107.64m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
29 Aug 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 85107.64m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
26 Aug 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 85107.64m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
23 Aug 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 85107.64m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
19 Aug 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 82731.16m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
16 Aug 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 82731.16m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
12 Aug 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 82731.16m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
04 Aug 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 82731.16m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
31 Jul 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2-35% completed, Malayil OHSR work progressing. Package 3- Ongoing 35% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Total laid qty 82731.16m. Parachantha OHSR -Work progressing . Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1