Status Date Overall Project Status Project Officer Contact
23 Apr 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Haunch works progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - Raft beam concrete completed. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
02 Apr 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Floor beam &slab work progressing. Column concreting second lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - PCC for foundation completed, steel work for column progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
29 Mar 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Floor beam &slab work progressing. Column concreting second lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - PCC for foundation completed,steel work for column progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
25 Mar 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Floor beam &slab work progressing. Column concreting second lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - PCC for foundation completed,steel work for column progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
20 Mar 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Floor beam &slab work progressing. Column concreting second lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - PCC for foundation completed,steel work for column progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
18 Mar 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Floor beam &slab work progressing. Column concreting second lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - PCC for foundation completed,steel work for column progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
15 Mar 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Floor beam steel work progressing. Column concreting second lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - PCC for foundation completed. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
12 Mar 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Floor beam steel work progressing. Column concreting second lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - PCC for foundation completed. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
10 Mar 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Floor beam steel work progressing. Column concreting second lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - PCC for foundation completed. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
07 Mar 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Floor beam steel work progressing. Column concreting second lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - PCC for foundation completed. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1