| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Dec 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara and Parachantha – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 29 Dec 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara and Parachantha – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 26 Dec 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara and Parachantha – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 22 Dec 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara and Parachantha – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 16 Dec 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 05 Dec 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 02 Dec 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 26 Nov 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 15 Nov 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 07 Nov 2025 | Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. | Alappuzha KIIFB - AEE 1 |