Overall Project Status

Status Date Overall Project Status Project Officer Contact
31 Dec 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara and Parachantha – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. 45% completed. Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
29 Dec 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara and Parachantha – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. 45% completed. Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
26 Dec 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara and Parachantha – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. 45% completed. Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
22 Dec 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara and Parachantha – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. 45% completed. Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
16 Dec 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
05 Dec 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
02 Dec 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
26 Nov 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
15 Nov 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – Work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1
07 Nov 2025 Package 1- Completed. After getting HT connection Raw water pumping main charged. Package 2- Malayil OHSR work progressing.40% completed. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara – work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work progressing. Parachantha OHSR -Work progressing . 45% completed. Package 5 - Completed and commissioned. Alappuzha KIIFB - AEE 1