- Home
- KIIFB-WSS to Ala, Puliyoor, Budhanoor, P...
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality
Project |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality |
Project Code |
ALPKIIFB0919495 |
Type |
Main project |
Funding Agency |
KIIFB |
Category |
KIIFB WATER SUPPLY SCHEME |
Type of scheme |
Water Supply |
Scheme |
KIIFB |
Description |
WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths & Chengannur Municipality in Alappuzha District.
The work includes the Renovation of existing intake well cum pump house, Substation and Power line extension at Intake Pump house Kolamukkam, Supply & Laying Raw water pumping main, Construction of 35 MLD WTP at Nikirumpuram, Laying Clear water Transmission Mains, construction of OHSR -8 nos and Providing Distribution system in all panchayats and Municipality .
|
Status |
On-going |
District |
Alappuzha |
Executing Office |
KIIFB Projects (ALP) |
AS Amount (Rs) |
1991347397
|
AS Number |
WRD025-24-PA-01 |
TS Amount (Rs) |
|
TS Number |
|
Total Bill Submitted (Rs) |
396079840 |
Total Bill Paid (Rs) |
396079840 |
Population Benefitted |
160659 |
Capacity in MLD |
35.00 |
Actual Project Completion Date |
Date is not specified |
Coverage |
Ala, Puliyoor, Budhanoor, Pandand, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality. |
Implementation Schedule |
Download |
Work Plan |
Download |
Packages
No. |
Project Name |
Location |
View |
1 |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package I |
KIIFB Projects(ALP) |
|
2 |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality-Package II |
KIIFB Projects(ALP) |
|
3 |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality ,Package-III |
KIIFB Projects(ALP) |
|
4 |
KIIFB-WSS to Ala, Puliyoor, Budhanoor, Pandanad, Mulakkuzha, Venmony Panchayaths and Chengannur Municipality,Package-IV |
KIIFB Projects(ALP) |
|
5 |
KIIFB-WSS to Ala , Puliyoor, Budhanoor. Pandanad. Mulakkuzha, Venmony Panchayaths and Chenganoor Municipality in Alappuzha District Package V- Urgent pipe laying in connection with road renovation works of PWD |
KIIFB Projects(ALP) |
|
Overall Project Status
Status Date |
Overall Project Status |
Project Officer |
Contact |
05 Jun 2023 |
As per the minutes of the meeting held on 03-05-2023 at KIIFB Main Conference Hall, KWA was directed to seek Government AS
by revising the schedule in two phases. KIIFB would take up the 1st phase now. ie. 50% of new proposal = 50% of Rs.434.443Cr. = Rs.217.221Cr. as Phase 1 . The DPR for Phase 1 for the subject work amounting to ₹217.221 crores is submitted for revised Administrative Sanction. Packages 1, 2, 3, 5 and additional works of new well and municipality road restoration are included in
the Phase 1 of the DER. Package I- Construction of 35 MLD WTP completed. The trial running and commissioning will de done after getting power connection . For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam concrete work completed on 1/06/2023. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13143m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid . Package III- Work tendered, 3 times extended, no bidders received. Package V - works completed. The package IV work amounting to Rs 206 crore which is included in 2 nd phase is placed in the JJM reappropriation |
Kottayam Project Dn AEE2 KIFFB |
|
25 May 2023 |
Package I- Construction of 35 MLD WTP completed. The trial running and commissioning will de done after getting power connection . For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13143m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid . Package III- Work tendered, 3 times extended, no bidders received. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - works completed. |
Kottayam Project Dn AEE2 KIFFB |
|
11 Apr 2023 |
Package I- Construction of 35 MLD WTP completed. The trial running and commissioning will de done after getting power connection . For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13143m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid . Package III- Work retendered and the due date extended up to 19.04.2023. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - works completed. |
Alappuzha KIIFB - AE 1 |
|
11 Apr 2023 |
Package I- Construction of 35 MLD WTP completed. The trial running and commissioning will be done after getting power connection. For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13143m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid . Package III- Work tendered. The due date extended to 20.03.2023. Technical Bid opening on 21.03.2023.. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - Pipe laying- 110mm PVC pipe 5397m laid, 90mm PVC pipe 7525m, and 160mm PVC 2068m ,200mm DI 989m, 250mm DI 580m laid |
Alappuzha KIIFB - AE 1 |
|
18 Mar 2023 |
Package I- Construction of 35 MLD WTP completed. Erection of 270 Hp raw water pump sets completed. For electrical connection to RWPH and WTP the fund demanded by KSEB deposited to KSEB section office. Package II Concreting of raft foundation for OHSR is completed on 12/7/2022. Column concreting up to the plinth level is completed. Plinth beam reinforcement work is in progress. Pipe laying- 110mm PVC pipe 11164m laid, 160mm PVC pipeline 13143m, and 90mm PVC pipe 7251m laid. 250 mm DI Pipe 444m laid. 200 mm DI Pipe 446 m laid . Package III- Work tendered. The due date extended to 20.03.2023. Technical Bid opening on 21.03.2023.. Package IV- The estimate submitted for TS is returned for want of revised AS. Package V - Pipe laying- 110mm PVC pipe 5397m laid, 90mm PVC pipe 7525m, and 160mm PVC 2068m ,200mm DI 989m, 250mm DI 580m laid |
Alappuzha KIIFB - AE 1 |
|
No project review have been added to this project
Duration & Sanction dates
Date of start of Project |
07/09/2019 |
Scheduled date of Completion of the Project |
31 Dec 2022 |
Expected date of Completion |
30/06/2023 |