| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 03 Mar 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Floor beam steel work progressing. Column concreting second lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - PCC for foundation completed. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 01 Mar 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Plinth beam work completed. Column concreting second lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - Earth work excavation for foundation completed. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 28 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Plinth beam work completed. Column concreting second lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - Earth work excavation for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 27 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Plinth beam work completed. Column concreting second lift progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - Earth work excavation for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 25 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Plinth beam work completed. Column concreting first lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - Earth work for foundation progressing. Package 5-Completed and commissioned. Meeting with Hon.Minister conducted. | Alappuzha KIIFB - AEE 1 | |
| 24 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Plinth beam work completed. Column concreting first lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - Earth work for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 22 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Plinth beam work completed. Column concreting first lift completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - Earth work for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 21 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Plinth beam work completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - Earth work for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 20 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara – Plinth beam work completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work is progressing. Parachantha OHSR - Earth work for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 19 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Ongoing 10% completed. Agreement executed on 08-07-2024.OHSR Kalarithara - Compound wall work progressing. Plinth beam work completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Parachantha OHSR -Footing work completed. Earth work for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 |