| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 05 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 04 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 03 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 01 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 31 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 30 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 29 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for OHSR foundation completed. Steel reinforcement work of column progressing.200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR PCC for foundation completed. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 28 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for OHSR foundation completed. Steel reinforcement work of column progressing.200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR PCC for foundation completed. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 27 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for OHSR foundation completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR PCC for foundation completed. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 25 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for OHSR foundation completed. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR PCC for foundation completed. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 |