| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara - Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Parachantha OHSR -Footing work completed. Earth work for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 17 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara - Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Parachantha OHSR -Footing work completed. Earth work for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 15 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara - Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Parachantha OHSR -Footing work completed. Earth work for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 14 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara - Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Parachantha OHSR -Footing work completed. Earth work for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 13 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara - Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Parachantha OHSR -Footing work completed. Earth work for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 12 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work completed.Plinth beam reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work completed.Earth work for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 11 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work completed.Plinth beam reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work completed.Earth work for foundation progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 10 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work completed.Plinth beam steel work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 07 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work completed.Plinth beam steel work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 | |
| 06 Feb 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work progressing. Package 5-Completed and commissioned. | Alappuzha KIIFB - AEE 1 |