Overall Project Status

Status Date Overall Project Status Project Officer Contact
18 Feb 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara - Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Parachantha OHSR -Footing work completed. Earth work for foundation progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
17 Feb 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara - Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Parachantha OHSR -Footing work completed. Earth work for foundation progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
15 Feb 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara - Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Parachantha OHSR -Footing work completed. Earth work for foundation progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
14 Feb 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara - Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Parachantha OHSR -Footing work completed. Earth work for foundation progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
13 Feb 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3- Agreement executed on 08-07-2024.OHSR Kalarithara - Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing. Parachantha OHSR -Footing work completed. Earth work for foundation progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
12 Feb 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work completed.Plinth beam reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work completed.Earth work for foundation progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
11 Feb 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work completed.Plinth beam reinforcement work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work completed.Earth work for foundation progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
10 Feb 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work completed.Plinth beam steel work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
07 Feb 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work completed.Plinth beam steel work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1
06 Feb 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. Plinth beam work progressing. 200,450,500mm DI and 90,110,160mm uPVC pipe laying work at Mulakkuzha pt is progressing.Parachantha OHSR -Footing work progressing. Package 5-Completed and commissioned. Alappuzha KIIFB - AEE 1