| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 13 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 10 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 09 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 08 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 07 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 06 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 04 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 03 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying started. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 02 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 01 Jan 2025 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation started. Pipe laying work at Mulakkuzha pt is progressing. Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 |