Overall Project Status

Status Date Overall Project Status Project Officer Contact
13 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
10 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
09 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
08 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
07 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
06 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
04 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
03 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing.200,500mm DI pipe laying started. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
02 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation completed. Pipe laying work at Mulakkuzha pt is progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
01 Jan 2025 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress. Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Compound wall work progressing. PCC for foundation started. Pipe laying work at Mulakkuzha pt is progressing. Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1