| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 31 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara - Compound wall work progressing. Earthwork excavation for foundation completed. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 30 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Earthwork excavation for foundation started. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 28 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Earthwork excavation for foundation started. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 27 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Earthwork excavation for foundation started. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 26 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Earthwork excavation for foundation started. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 24 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Earthwork excavation for foundation started. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 23 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Earthwork excavation for foundation started. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 22 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Earthwork excavation for foundation started. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 21 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Earthwork excavation for foundation started. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 20 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Earthwork excavation for foundation started. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 |