| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 19 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Earthwork excavation for foundation started. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 18 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 17 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 16 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 12 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 11 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 10 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 09 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 07 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 | |
| 06 Dec 2024 | Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned | Alappuzha KIIFB - AEE 1 |