Overall Project Status

Status Date Overall Project Status Project Officer Contact
19 Dec 2024 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Earthwork excavation for foundation started. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
18 Dec 2024 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
17 Dec 2024 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
16 Dec 2024 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
12 Dec 2024 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
11 Dec 2024 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
10 Dec 2024 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
09 Dec 2024 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
07 Dec 2024 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1
06 Dec 2024 Package 1-99% Completed. After getting HT connection Raw water pumping main charged. Package 2-Ongoing 35% completed. Very slow progress Package 3-LOA issued and agreement executed on 08-07-2024.OHSR-Kalarithara -Site clearing work completed. Compound wall work progressing. Pipe laying work at Mulakkuzha pt is progressing. .Package 5-Completed and commissioned Alappuzha KIIFB - AEE 1