| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 18 Jul 2024 | Package-I-30 % completed, 271 nos FHTCs are given,Total Pipe laid till date-4742 m (Heavy rain affect the progress of work) . Package-II-70 % completed , 2463 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS in progress ) -- Package-III-69 % completed ,890 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed) . Heavy rain affects progress of work. | Kollam WS Sn 2 - AE | |
| 15 Jul 2024 | Package-I-30 % completed, 271 nos FHTCs are given,Total Pipe laid till date-4742 m (Heavy rain affect the progress of work) . Package-II-70 % completed , 2463 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-69 % completed ,890 nos FHTCs are given, Total Pipe laid till date- 12300 m . Work in progress. | Kollam WS Sn 2 - AE | |
| 12 Jul 2024 | Package-I-30 % completed, 271 nos FHTCs are given,Total Pipe laid till date-4742 m (FHTCS and pipe laying in progress) . Package-II-70 % completed , 2463 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-69 % completed ,890 nos FHTCs are given, Total Pipe laid till date- 12300 m . Work in progress. | Kollam WS Sn 2 - AE | |
| 09 Jul 2024 | Package-I-30 % completed, 271 nos FHTCs are given,Total Pipe laid till date-4742 m (FHTCS and pipe laying in progress) . Package-II-69 % completed , 2393 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-68 % completed ,850 nos FHTCs are given, Total Pipe laid till date- 12300 m . Work in progress. | Kollam WS Sn 2 - AE | |
| 05 Jul 2024 | Package-I-30 % completed, 263 nos FHTCs are given,Total Pipe laid till date-4252 m (FHTCS and pipe laying in progress . Package-II-69 % completed , 2373 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-68 % completed ,837 nos FHTCs are given, Total Pipe laid till date- 12300 m . Work in progress. | Kollam WS Sn 2 - AE | |
| 02 Jul 2024 | Package-I-30 % completed, 263 nos FHTCs are given,Total Pipe laid till date-4252 m (FHTCS and pipe laying in progress . Package-II-67 % completed , 2359 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-67 % completed ,817 nos FHTCs are given, Total Pipe laid till date- 12300 m . Heavy rain affects the progress of works. | Kollam WS Sn 2 - AE | |
| 29 Jun 2024 | Package-I-30 % completed, 263 nos FHTCs are given,Total Pipe laid till date-4252 m (FHTCS and pipe laying in progress . Package-II-67 % completed , 2359 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-67 % completed ,817 nos FHTCs are given, Total Pipe laid till date- 12300 m . Heavy rain affects the progress of works. | Kollam WS Sn 2 - AE | |
| 26 Jun 2024 | Package-I-30 % completed, 243 nos FHTCs are given,Total Pipe laid till date-4010 m (FHTCS and pipe laying in progress . Package-II-67 % completed , 2349 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-67 % completed ,817 nos FHTCs are given, Total Pipe laid till date- 12300 m . Heavy rain affects the progress of works. | Kollam WS Sn 2 - AE | |
| 24 Jun 2024 | Package-I-30 % completed, 233 nos FHTCs are given,Total Pipe laid till date-3938 m (FHTCS and pipe laying in progress . Package-II-67 % completed , 2256 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-67 % completed ,817 nos FHTCs are given, Total Pipe laid till date- 12300 m . | Kollam WS Sn 2 - AE | |
| 19 Jun 2024 | Package-I-30 % completed, 220 nos FHTCs are given,Total Pipe laid till date-3860 m (FHTCS and pipe laying in progress . Package-II-67 % completed , 2225 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS and pipe laying in progress ) -- Package-III-66 % completed ,805 nos FHTCs are given, Total Pipe laid till date- 12300 m . | Kollam WS Sn 2 - AE |