| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 16 Dec 2024 | Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 85 % completed , 3415 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) | Kollam WS Sn 2 - AE | |
| 09 Dec 2024 | Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 85 % completed , 3415 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). | Kollam WS Sn 2 - AE | |
| 04 Dec 2024 | Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 83 % completed , 3306 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). | Kollam WS Sn 2 - AE | |
| 30 Nov 2024 | Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 83 % completed , 3306 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). | Kollam WS Sn 2 - AE | |
| 25 Nov 2024 | Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 81 % completed , 3217 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). | Kollam WS Sn 2 - AE | |
| 20 Nov 2024 | Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 80 % completed , 3171 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). | Kollam WS Sn 2 - AE | |
| 14 Nov 2024 | Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 532 nos FHTCs are given,Total Pipe laid till date-5620 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 80 % completed , 3151 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). | Kollam WS Sn 2 - AE | |
| 11 Nov 2024 | Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 532 nos FHTCs are given,Total Pipe laid till date-5100 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 79 % completed , 3151 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). | Kollam WS Sn 2 - AE | |
| 07 Nov 2024 | Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 531 nos FHTCs are given,Total Pipe laid till date-5100 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 79 % completed , 3111 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). | Kollam WS Sn 2 - AE | |
| 05 Nov 2024 | Package-1-Old Muncipal area in Kollam corporation - 42 % completed, 460 nos FHTCs are given,Total Pipe laid till date-5100 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 71 % completed ,1066 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 79 % completed , 3092 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). | Kollam WS Sn 2 - AE |