Status Date Overall Project Status Project Officer Contact
16 Dec 2024 Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 85 % completed , 3415 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress) Kollam WS Sn 2 - AE
09 Dec 2024 Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 85 % completed , 3415 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). Kollam WS Sn 2 - AE
04 Dec 2024 Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 83 % completed , 3306 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). Kollam WS Sn 2 - AE
30 Nov 2024 Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 83 % completed , 3306 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). Kollam WS Sn 2 - AE
25 Nov 2024 Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 81 % completed , 3217 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). Kollam WS Sn 2 - AE
20 Nov 2024 Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 567 nos FHTCs are given,Total Pipe laid till date-6045.6 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 80 % completed , 3171 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). Kollam WS Sn 2 - AE
14 Nov 2024 Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 532 nos FHTCs are given,Total Pipe laid till date-5620 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 80 % completed , 3151 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). Kollam WS Sn 2 - AE
11 Nov 2024 Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 532 nos FHTCs are given,Total Pipe laid till date-5100 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 79 % completed , 3151 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). Kollam WS Sn 2 - AE
07 Nov 2024 Package-1-Old Muncipal area in Kollam corporation - 43 % completed, 531 nos FHTCs are given,Total Pipe laid till date-5100 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 72 % completed ,1104 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 79 % completed , 3111 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). Kollam WS Sn 2 - AE
05 Nov 2024 Package-1-Old Muncipal area in Kollam corporation - 42 % completed, 460 nos FHTCs are given,Total Pipe laid till date-5100 m (Work in progress). Package-2- Sakthikulangara & Thrikkadavoor zone - 71 % completed ,1066 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed), FHTC works progress. Package-3-Vadakkevila- Eravipuram & Kilikolloor zone - 79 % completed , 3092 nos FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ). Kollam WS Sn 2 - AE