| Status Date | Overall Project Status | Project Officer | Contact |
|---|---|---|---|
| 24 Aug 2024 | Package-I-34 % completed, 327 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-II-76 % completed , 2828 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-III-69 % completed ,985 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed, Heavy rain affects progress of work) | Kollam WS Sn 2 - AE | |
| 22 Aug 2024 | Package-I-34 % completed, 327 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-II-76 % completed , 2828 FHTCs are given, Total Pipe laid till date-11173 m(FHTCS in progress ) -- Package-III-69 % completed ,985 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed, Heavy rain affects progress of work) | Kollam WS Sn 2 - AE | |
| 16 Aug 2024 | Package-I-32 % completed, 319 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-II-74 % completed , 2828 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS in progress ) -- Package-III-69 % completed ,985 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed, Heavy rain affects progress of work) | Kollam WS Sn 2 - AE | |
| 13 Aug 2024 | Package-I-32 % completed, 319 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-II-74 % completed , 2800 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS in progress ) -- Package-III-69 % completed ,984 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed, Heavy rain affects progress of work) | Kollam WS Sn 2 - AE | |
| 10 Aug 2024 | Package-I-32 % completed, 319 nos FHTCs are given,Total Pipe laid till date-5051 m Work in progress) . Package-II-74 % completed , 2783 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS in progress ) -- Package-III-69 % completed ,984 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed) . | Kollam WS Sn 2 - AE | |
| 06 Aug 2024 | Package-I-30 % completed, 300 nos FHTCs are given,Total Pipe laid till date-4742 m (Heavy rain affect the progress of work) . Package-II-74 % completed , 2749 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS in progress ) -- Package-III-69 % completed ,984 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed) . | Kollam WS Sn 2 - AE | |
| 01 Aug 2024 | Package-I-30 % completed, 300 nos FHTCs are given,Total Pipe laid till date-4742 m (Heavy rain affect the progress of work) . Package-II-72 % completed , 2676 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS in progress ) -- Package-III-69 % completed ,983 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed) . | Kollam WS Sn 2 - AE | |
| 29 Jul 2024 | Package-I-30 % completed, 271 nos FHTCs are given,Total Pipe laid till date-4742 m (Heavy rain affect the progress of work) . Package-II-72 % completed , 2634 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS in progress ) -- Package-III-69 % completed ,940 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed) . | Kollam WS Sn 2 - AE | |
| 25 Jul 2024 | Package-I-30 % completed, 271 nos FHTCs are given,Total Pipe laid till date-4742 m (Heavy rain affect the progress of work) . Package-II-72 % completed , 2540 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS in progress ) -- Package-III-69 % completed ,913 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed) . | Kollam WS Sn 2 - AE | |
| 22 Jul 2024 | Package-I-30 % completed, 271 nos FHTCs are given,Total Pipe laid till date-4742 m (Heavy rain affect the progress of work) . Package-II-70 % completed , 2530 FHTCs are given, Total Pipe laid till date-10170 m(FHTCS in progress ) -- Package-III-69 % completed ,906 nos FHTCs are given, Total Pipe laid till date- 12300 m(laying completed) . Heavy rain affects progress of work. | Kollam WS Sn 2 - AE |